3706 S CHERRYWOOD AVE 90018

Certificate Information: 3706 S CHERRYWOOD AVE 90018

Application / Permit
21016-10000-30706
Plan Check / Job No.
B21LA17686
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
AN INTERIOR REMODEL TO AN EXISTING SINGLE FAMILY RESIDENCE. WORK TO INCLUDE: RELOCATE EXISTING KITCHEN TO DINING ROOM AND CONVERSION OF AN EXISTING KITCHEN INTO A NEW BEDROOM/POWDER ROOM. CONVERSION OF AN EXISTING FAMILY ROOM INTO A NEW BEDROOM/BATHROOM AND WALK-IN CLOSET. WORK TO ALSO INCLUDE REPLACE (14) WINDOWS IN THE SAME SIZE AND LOCATIONS. ALL WORK DONE PER WFPP
Permit Issued
Issued on 12/27/2021
Issuing Office
Current Status
Permit Finaled on 10/23/2023

Permit Application Status History

Submitted 9/23/2021 APPLICANT
Assigned to Plan Check Engineer 9/23/2021 LUKE GONZALES
Corrections Issued 9/23/2021 LUKE GONZALES
Building Plans Picked Up 10/28/2021 APPLICANT
Plan Check Approved 12/13/2021 RICARDO RAMIREZ
Issued 12/27/2021 APPLICANT
Permit Finaled 10/21/2023 ALEJANDRO DE ARTOLA

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/22/2021 THOMAS LANG
Sewer availability Cleared 10/22/2021 THOMAS LANG

Contact Information

Contractor Roston Thomas Construction; Lic. No.: 954624-B P O BOX 351292      LOS ANGELES, CA 90035

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 7/23/2022 Corrections Issued JOSEPH MCGARRY
ELECTRICAL-Rough 7/23/2022 Not Ready for Inspection JOSEPH MCGARRY
Gas Test 7/23/2022 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Rough 7/23/2022 Not Ready for Inspection JOSEPH MCGARRY
ELECTRICAL-Rough 8/20/2022 Off-Hour Fees Due
Floor/Roof Diaphrgm/Shear Wall 8/20/2022 Off-Hour Fees Due
HVAC-Rough 8/20/2022 Off-Hour Fees Due
PLUMBING-Rough 8/20/2022 Off-Hour Fees Due
Rough-Elec/Plmb/HVAC 8/20/2022 Off-Hour Fees Due
BUILDING-Rough-Frame 8/23/2022 Off-Hour Fees Due
ELECTRICAL-Rough 8/23/2022 Off-Hour Fees Due
Floor/Roof Diaphrgm/Shear Wall 8/23/2022 Off-Hour Fees Due
HVAC-Rough 8/23/2022 Off-Hour Fees Due
PLUMBING-Rough 8/23/2022 Off-Hour Fees Due
Rough-Elec/Plmb/HVAC 8/23/2022 Off-Hour Fees Due
Wood Frame 8/23/2022 Off-Hour Fees Due
BUILDING-Rough-Frame 8/25/2022 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 8/25/2022 No Access for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 8/25/2022 No Access for Inspection ANTHONY EGSON
HVAC-Rough 8/25/2022 No Access for Inspection ANTHONY EGSON
PLUMBING-Rough 8/25/2022 No Access for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 8/27/2022 Partial Inspection JOSEPH MCGARRY
ELECTRICAL-Rough 8/27/2022 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 8/27/2022 Partial Inspection JOSEPH MCGARRY
HVAC-Rough 8/27/2022 Partial Approval JOSEPH MCGARRY
PLUMBING-Rough 8/27/2022 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 9/10/2022 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 9/10/2022 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 9/10/2022 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 9/10/2022 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 9/10/2022 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 9/10/2022 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 9/10/2022 Approved ALEJANDRO DE ARTOLA
Pre-Inspection 9/19/2022 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/1/2022 Approved ALAN MORELOS
Floor/Roof Diaphrgm/Shear Wall 10/1/2022 Off-Hour Fees Due
Shower Pan 10/1/2022 Approved ALAN MORELOS
Shower Pan 10/1/2022 Off-Hour Fees Due
BUILDING-Rough-Frame 3/25/2023 Partial Approval HERBERT GIRON
Final 7/15/2023 Corrections Issued JOHN TCHANG
Final 7/15/2023 Off-Hour Fees Due
SGSOV-Seismic Gas S/O Valve 7/15/2023 Off-Hour Fees Due
SGSOV-Seismic Gas S/O Valve 7/15/2023 SGSOV Not Ready JOHN TCHANG
Smoke Detectors 7/15/2023 Not Ready for Inspection JOHN TCHANG
Smoke Detectors 7/15/2023 Off-Hour Fees Due
Final 10/14/2023 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 10/14/2023 SGSOV Approved LILIANA PORTILLO
Smoke Detectors 10/14/2023 Not Ready for Inspection LILIANA PORTILLO
Final 10/21/2023 Permit Finaled ALEJANDRO DE ARTOLA
Smoke Detectors 10/21/2023 Approved ALEJANDRO DE ARTOLA