649 E PALMS BLVD 90291

Certificate Information: 649 E PALMS BLVD 90291

Application / Permit
21016-10000-30700
Plan Check / Job No.
B21LA17684
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR AND EXTERIOR REMODEL TO EXISTING TWO STORY SFD PER ADM-2022-2755-CEX (NOTE TO DCP: EXTERIOR WORK INCLUDES NEW HIP ROOF, ENCLOSE 1ST FLOOR PORCH TO HABITABLE AREA, NEW WINDOWS / DOORS)
Permit Issued
Issued on 8/1/2022
Issuing Office
Metro
Current Status
Permit Finaled on 4/5/2024

Permit Application Status History

Submitted 10/5/2021 APPLICANT
Assigned to Plan Check Engineer 11/9/2021 STARR CHEN
Corrections Issued 11/16/2021 STARR CHEN
Quality Review Completed 11/22/2021 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 11/29/2021 APPLICANT
Applicant returned to address corrections 1/24/2022 STARR CHEN
Applicant returned to address corrections 4/26/2022 AUNG SOE
Applicant returned to address corrections 7/6/2022 AUNG SOE
Plan Check Approved 7/7/2022 AUNG SOE
Issued 8/1/2022 APPLICANT
Permit Finaled 4/5/2024 HERBERT GIRON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/15/2022 DINAH GARIN
Sewer availability Cleared 3/15/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 3/22/2022 DINAH GARIN
Coastal Zone Cleared 6/17/2022 YINGSHI HUANG
Specific Plan Cleared 7/7/2022 IRA BROWN

Contact Information

Contractor Vallernaud Construction Inc; Lic. No.: 1025929-B 11826 ALLASEBA DR      LOS ANGELES, CA 90066

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/4/2022 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 10/6/2022 Approved DAVID FEILER
Deputy Drilled-In Anchors 10/18/2022 No Access for Inspection DAVID FEILER
Special/Order Compliance 4/6/2023 Corrections Issued HERBERT GIRON
HVAC-Rough 7/6/2023 Approved EVAN COOPER
ELECTRICAL-Rough 7/12/2023 Approved EVAN COOPER
PLUMBING-Rough 7/12/2023 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 7/21/2023 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 8/18/2023 Partial Approval HERBERT GIRON
Wood Frame 8/18/2023 Not Ready for Inspection HERBERT GIRON
Deputy Wood Construction 8/24/2023 Conditional Approval MICHAEL PELHAM
BUILDING-Rough-Frame 8/25/2023 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 8/25/2023 Approved HERBERT GIRON
Interior/Exterior Lathing 8/25/2023 Not Ready for Inspection HERBERT GIRON
Footing/Foundation/Slab 8/29/2023 Not Ready for Inspection TEMISTOCLES CAAL
Insulation 8/29/2023 Not Ready for Inspection TEMISTOCLES CAAL
BUILDING-Rough-Frame 9/27/2023 Approved HERBERT GIRON
Insulation 9/27/2023 Approved HERBERT GIRON
Interior/Exterior Lathing 9/27/2023 Partial Approval HERBERT GIRON
Drywall Nailing 10/5/2023 Approved HERBERT GIRON
Final 10/5/2023 Corrections Issued HERBERT GIRON
Interior/Exterior Lathing 10/26/2023 Approved HERBERT GIRON
Shower Pan 10/26/2023 Approved HERBERT GIRON
Gas Test 3/14/2024 Approved HERBERT GIRON
PLUMBING-Final 3/14/2024 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 3/14/2024 SGSOV Approved HERBERT GIRON
ELECTRICAL-Final 3/18/2024 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Final 3/19/2024 Approved HERBERT GIRON
Service/Power Release 3/19/2024 Approved HERBERT GIRON
HVAC-Final 3/28/2024 Corrections Issued HERBERT GIRON
Smoke Detectors 3/28/2024 Approved HERBERT GIRON
Final 4/3/2024 Corrections Issued HERBERT GIRON
Green Building Final 4/3/2024 Approved HERBERT GIRON
HVAC-Final 4/3/2024 Approved HERBERT GIRON
Final 4/5/2024 Permit Finaled HERBERT GIRON