2229 S BRONSON AVE 90018

Certificate Information: 2229 S BRONSON AVE 90018

Application / Permit
21016-10000-30678
Plan Check / Job No.
B21LA17668
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: ADDITION TO (E) GARAGE AND CONVERT THE ENTIRE BUILDING TO 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
Permit Issued
Issued on 9/22/2022
Issuing Office
Current Status
CofO Issued on 6/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/5/2022 APPLICANT
Assigned to Plan Check Engineer 2/3/2022 DANIEL YIP
Corrections Issued 2/7/2022 DANIEL YIP
Quality Review Completed 2/7/2022 LIPING TENG
Applicant returned to address corrections 6/16/2022 DANIEL YIP
Plan Check Approved 8/30/2022 DANIEL YIP
Issued 9/22/2022 APPLICANT
CofO in Progress 6/7/2024 JUSTIN HAWLEY
CofO Issued 6/10/2024 DEROLD HAUFF
Permit Finaled 6/10/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/16/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 3/21/2022 JEANETTE VONG
Sewer availability Cleared 3/21/2022 JEANETTE VONG
Low Impact Development Cleared 7/26/2022 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 7/27/2022 JEANETTE VONG
Community Plan Implem. Overlay Cleared 8/24/2022 KYLE WINSTON

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/17/2023 Conditional Approval CALEB MEISTER
PLUMBING-Rough 5/22/2023 Partial Approval CALEB MEISTER
Footing/Foundation/Slab 5/25/2023 Approved CALEB MEISTER
ELECTRICAL-Rough 7/7/2023 Not Ready for Inspection CALEB MEISTER
HVAC-Rough 7/7/2023 Not Ready for Inspection CALEB MEISTER
PLUMBING-Rough 7/7/2023 Not Ready for Inspection CALEB MEISTER
Wood Frame 7/7/2023 Not Ready for Inspection CALEB MEISTER
ELECTRICAL-Rough 7/13/2023 Corrections Issued CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 7/13/2023 Approved CALEB MEISTER
HVAC-Rough 7/13/2023 Approved CALEB MEISTER
PLUMBING-Rough 7/13/2023 Approved CALEB MEISTER
Interior/Exterior Lathing 8/3/2023 Partial Approval CALEB MEISTER
Insulation 8/15/2023 Approved CALEB MEISTER
BUILDING-Rough-Frame 8/29/2023 Approved CALEB MEISTER
Drywall Nailing 8/29/2023 Approved CALEB MEISTER
Green Building Rough 8/29/2023 Approved CALEB MEISTER
MERV13>=Rough 8/29/2023 Approved CALEB MEISTER
Interior/Exterior Lathing 9/28/2023 Approved CALEB MEISTER
ELECTRICAL-Rough 1/11/2024 Not Ready for Inspection BRENDAN MORELLI
Gas Test 1/11/2024 Partial Approval BRENDAN MORELLI
Sewer 1/11/2024 Approved BRENDAN MORELLI
Underground Mechanical 1/11/2024 Corrections Issued BRENDAN MORELLI
ELECTRICAL-Final 6/4/2024 Approved JUSTIN HAWLEY
Final 6/4/2024 OK to Issue CofO JUSTIN HAWLEY
Green Building Final 6/4/2024 Approved JUSTIN HAWLEY
HVAC-Final 6/4/2024 Approved JUSTIN HAWLEY
MERV13>=Final 6/4/2024 Approved JUSTIN HAWLEY
PLUMBING-Final 6/4/2024 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 6/4/2024 SGSOV Approved JUSTIN HAWLEY
Smoke Detectors 6/4/2024 Approved JUSTIN HAWLEY