9719 W HEATHER ROAD 90210
Certificate Information: 9719 W HEATHER ROAD 90210
- Application / Permit
- 21016-10000-30523
- Plan Check / Job No.
- B21LA17542
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT INTERIOR STAIR INTO ELEVATOR.
- Permit Issued
- Issued on 1/6/2022
- Issuing Office
- Current Status
- Permit Finaled on 7/12/2022
Permit Application Status History
| Submitted | 9/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/22/2021 | LAWRENCE QUIRANTE |
| Corrections Issued | 9/23/2021 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 10/28/2021 | SHANGQIN XIE |
| Plan Check Approved | 11/16/2021 | SAMUEL GONZALEZ |
| Building Plans Picked Up | 11/30/2021 | APPLICANT |
| Issued | 1/6/2022 | APPLICANT |
| Permit Finaled | 7/11/2022 | RAUL BARAJAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/16/2021 | LAWRENCE QUIRANTE |
Contact Information
| Contractor | Epic Construction Inc; Lic. No.: 574409-B | 2808 OREGON COURT L5 TORRANCE, CA 90503 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/1/2022 | Approved | RAUL BARAJAS |
| Footing/Foundation/Slab | 3/1/2022 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 3/30/2022 | Approved | RAUL BARAJAS |
| ELECTRICAL-Rough | 3/30/2022 | Approved | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/30/2022 | Approved | RAUL BARAJAS |
| HVAC-Rough | 3/30/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Insulation | 3/30/2022 | Approved | RAUL BARAJAS |
| PLUMBING-Rough | 3/30/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Wood Frame | 3/30/2022 | Approved | RAUL BARAJAS |
| Drywall Nailing | 4/8/2022 | Approved | RAUL BARAJAS |
| ELECTRICAL-Final | 7/11/2022 | Approved | RAUL BARAJAS |
| Final | 7/11/2022 | Permit Finaled | RAUL BARAJAS |
| HVAC-Final | 7/11/2022 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Final | 7/11/2022 | Not Ready for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 7/11/2022 | SGSOV Approved | RAUL BARAJAS |
| Smoke Detectors | 7/11/2022 | Approved | RAUL BARAJAS |