4850 W HOLLYWOOD BLVD 90027
Certificate Information: 4850 W HOLLYWOOD BLVD 90027
- Application / Permit
- 21016-10000-30266
- Plan Check / Job No.
- B21LA17380
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Veterinary Clinic
- Work Description
- Change of Use and Occupancy and Tenant Improvement of an existing 3,605 sq ft Tenant Space within an existing mixed use building. Add new non-structural Partitions, casework, and finishes. Interior work only
- Permit Issued
- Issued on 7/26/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/21/2021 | ZAW HAN |
| Corrections Issued | 11/9/2021 | ZAW HAN |
| Quality Review Completed | 11/10/2021 | KEN GILL |
| Building Plans Picked Up | 12/9/2021 | APPLICANT |
| Applicant returned to address corrections | 12/22/2021 | ZAW HAN |
| Plan Check Approved | 5/24/2022 | ZAW HAN |
| Issued | 7/26/2022 | APPLICANT |
| CofO in Progress | 8/27/2024 | RAFAEL CORTES |
| CofO Issued | 9/5/2024 | ERNESTO CORRAL |
| Permit Finaled | 9/5/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| Miscellaneous | Cleared | 11/30/2021 | RUBEN VASQUEZ |
| ZA Case | Cleared | 11/30/2021 | RUBEN VASQUEZ |
| ZA Case | Cleared | 11/30/2021 | RUBEN VASQUEZ |
| ZA Case | Cleared | 11/30/2021 | RUBEN VASQUEZ |
| ZA Case | Cleared | 11/30/2021 | RUBEN VASQUEZ |
| Roof/Waste drainage to street | Cleared | 12/14/2021 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 12/27/2021 | ABEL CASILLAS |
| Sewer availability | Cleared | 12/27/2021 | ABEL CASILLAS |
| "D" conditions | Cleared | 3/15/2022 | NOAH MCCOY |
| Comm Cor/Mini-Mall | Cleared | 3/15/2022 | NOAH MCCOY |
| Comm Cor/Mini-Mall | Cleared | 3/15/2022 | NOAH MCCOY |
| Miscellaneous | Cleared | 3/15/2022 | NOAH MCCOY |
| Specific Plan | Cleared | 3/21/2022 | ZAW HAN |
| Green Code | Cleared | 4/27/2022 | ZAW HAN |
| DAS Clearance | Cleared | 5/12/2022 | ZAW HAN |
Contact Information
| Architect | Rudolph,, Rebecca Alice; Lic. No.: C29756 | 3218 ATWATER AVENUE LOS ANGELES, CA 90039 |
| Contractor | S 3 Builders Inc; Lic. No.: 928330-B | P O BOX 11478 BURBANK, CA 91510 |
| Engineer | Tuchscher,, James Todd; Lic. No.: C77649 | 5503 E 2ND ST LONG BEACH, CA 90803 |
Inspector Information
| DAVID BURKHEAD, (213) 482-7294 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 3/14/2023 | Not Ready for Inspection | RONALD JIMENEZ |
| Green Building Final | 3/14/2023 | Not Ready for Inspection | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 3/14/2023 | SGSOV Not Ready | RONALD JIMENEZ |
| Smoke Detectors | 3/14/2023 | Not Ready for Inspection | RONALD JIMENEZ |
| Pre-Inspection | 1/24/2024 | Approved | JACOB MYERS |
| Final | 8/19/2024 | Not Ready for Inspection | MARTIN TAVITIAN |
| Green Building Final | 8/19/2024 | Not Ready for Inspection | MARTIN TAVITIAN |
| SGSOV-Seismic Gas S/O Valve | 8/19/2024 | SGSOV Not Ready | MARTIN TAVITIAN |
| Smoke Detectors | 8/19/2024 | Not Ready for Inspection | MARTIN TAVITIAN |
| Final | 8/22/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Final | 8/22/2024 | Approved | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 8/22/2024 | SGSOV Not Ready | RAFAEL CORTES |
| Smoke Detectors | 8/22/2024 | Approved | RAFAEL CORTES |
| Final | 8/27/2024 | OK to Issue CofO | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 8/27/2024 | SGSOV No Gas | RAFAEL CORTES |