9527-9529 N OSO AVE 91311

Certificate Information: 9527-9529 N OSO AVE 91311

Application / Permit
21016-10000-30224
Plan Check / Job No.
B21LA17342
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Conversion of attached garage into one story attached ADU per GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 10/26/2021
Issuing Office
Current Status
CofO Issued on 10/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/17/2021 APPLICANT
Assigned to Plan Check Engineer 9/20/2021 RAMA DABADGE
Corrections Issued 9/20/2021 RAMA DABADGE
Plan Check Approved 10/21/2021 RICARDO RAMIREZ
Issued 10/26/2021 APPLICANT
Building Plans Picked Up 10/27/2021 APPLICANT
CofO in Progress 9/9/2025 DAVID SCANTLIN
Permit Finaled 10/1/2025 JOHN JANSON
CofO Issued 10/1/2025 JOHN JANSON
Permit Finaled 10/1/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 9/23/2021 CARLOS AGUILERA
Sewer availability Cleared 9/23/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/14/2021 ABDULLAH SADOZAI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/23/2024 Approved DAVID SCANTLIN
Footing/Foundation/Slab 11/12/2024 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 3/17/2025 Not Ready for Inspection KRISTEN CAUSEY
ELECTRICAL-Rough 3/20/2025 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 3/20/2025 Approved DAVID SCANTLIN
PLUMBING-Rough 3/20/2025 Not Ready for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 4/1/2025 Corrections Issued KRISTEN CAUSEY
HVAC-Rough 4/8/2025 Approved DAVID SCANTLIN
PLUMBING-Rough 4/8/2025 Partial Approval DAVID SCANTLIN
Interior/Exterior Lathing 4/23/2025 Corrections Issued KRISTEN CAUSEY
BUILDING-Rough-Frame 4/24/2025 Approved DAVID SCANTLIN
Green Building Rough 4/24/2025 Approved DAVID SCANTLIN
Interior/Exterior Lathing 4/24/2025 Partial Approval DAVID SCANTLIN
Rough-Elec/Plmb/HVAC 4/24/2025 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 4/28/2025 Approved DAVID SCANTLIN
Green Building Rough 4/28/2025 Approved DAVID SCANTLIN
Shower Pan 4/28/2025 Not Ready for Inspection DAVID SCANTLIN
Green Building Final 7/10/2025 Not Ready for Inspection KRISTEN CAUSEY
Final 7/24/2025 Corrections Issued DAVID SCANTLIN
Green Building Final 7/24/2025 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 7/24/2025 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 7/24/2025 Approved DAVID SCANTLIN
Final 9/8/2025 OK to Issue CofO DAVID SCANTLIN
Green Building Final 9/8/2025 Approved DAVID SCANTLIN