925 N EDINBURGH AVE 90046
Certificate Information: 925 N EDINBURGH AVE 90046
- Application / Permit
- 21016-10000-30127
- Plan Check / Job No.
- B21LA17281
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING TWO CAR GARAGE INTO AN ADU PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 3/15/2022
- Issuing Office
- Current Status
- CofO Issued on 9/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2021 | SINA KHOSRAVI |
| Corrections Issued | 9/19/2021 | SINA KHOSRAVI |
| Applicant returned to address corrections | 11/17/2021 | TSE MING HUANG |
| Applicant returned to address corrections | 12/17/2021 | RAHEL BEYENE |
| Plan Check Approved | 1/14/2022 | RAHEL BEYENE |
| Issued | 3/15/2022 | APPLICANT |
| Building Plans Picked Up | 3/16/2022 | APPLICANT |
| CofO in Progress | 9/15/2023 | LILIANA PORTILLO |
| Permit Finaled | 9/25/2023 | DEROLD HAUFF |
| CofO Issued | 9/25/2023 | DEROLD HAUFF |
| Permit Finaled | 9/25/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/5/2021 | WALLIE JONG |
| Sewer availability | Cleared | 11/5/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 11/9/2021 | WALLIE JONG |
Contact Information
| No Data Available. |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Test | 3/24/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Pre-Inspection | 3/24/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 4/4/2022 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 4/11/2022 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Rough | 4/11/2022 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Rough | 4/11/2022 | Approved | STUART CHAPMAN |
| Sewer | 4/11/2022 | Partial Approval | STUART CHAPMAN |
| Wood Frame | 4/11/2022 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Final | 4/15/2022 | Not Ready for Inspection | JUSTIN CURTIS |
| ELECTRICAL-Rough | 4/21/2022 | Approved | ADAM ESCOTO |
| Service/Power Release | 4/21/2022 | Not Ready for Inspection | ADAM ESCOTO |
| HVAC-Rough | 5/26/2022 | Approved | JOSEPH MCGARRY |
| Insulation | 5/26/2022 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 5/26/2022 | Partial Approval | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 6/7/2022 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Final | 6/13/2022 | Corrections Issued | JOSEPH MCGARRY |
| Gas Test | 6/13/2022 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 11/29/2022 | SGSOV Not Ready | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 1/31/2023 | SGSOV Not Ready | MICHAEL LEWIS |
| Final | 6/14/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Final | 6/14/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 6/14/2023 | SGSOV Not Ready | LILIANA PORTILLO |
| Smoke Detectors | 6/14/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Final | 7/24/2023 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 7/24/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 7/24/2023 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Final | 8/31/2023 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 8/31/2023 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Final | 8/31/2023 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Final | 8/31/2023 | Approved | LILIANA PORTILLO |
| Smoke Detectors | 8/31/2023 | Approved | LILIANA PORTILLO |
| Final | 9/13/2023 | OK to Issue CofO | LILIANA PORTILLO |
| Green Building Final | 9/13/2023 | Approved | LILIANA PORTILLO |
| HVAC-Final | 9/13/2023 | Approved | LILIANA PORTILLO |