925 N EDINBURGH AVE 90046

Certificate Information: 925 N EDINBURGH AVE 90046

Application / Permit
21016-10000-30127
Plan Check / Job No.
B21LA17281
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING TWO CAR GARAGE INTO AN ADU PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 3/15/2022
Issuing Office
Current Status
CofO Issued on 9/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/16/2021 APPLICANT
Assigned to Plan Check Engineer 9/17/2021 SINA KHOSRAVI
Corrections Issued 9/19/2021 SINA KHOSRAVI
Applicant returned to address corrections 11/17/2021 TSE MING HUANG
Applicant returned to address corrections 12/17/2021 RAHEL BEYENE
Plan Check Approved 1/14/2022 RAHEL BEYENE
Issued 3/15/2022 APPLICANT
Building Plans Picked Up 3/16/2022 APPLICANT
CofO in Progress 9/15/2023 LILIANA PORTILLO
Permit Finaled 9/25/2023 DEROLD HAUFF
CofO Issued 9/25/2023 DEROLD HAUFF
Permit Finaled 9/25/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/5/2021 WALLIE JONG
Sewer availability Cleared 11/5/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 11/9/2021 WALLIE JONG

Contact Information

No Data Available.

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Test 3/24/2022 Partial Approval ALIZAH MAYAGOITIA
Pre-Inspection 3/24/2022 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 4/4/2022 Approved JOSEPH MCGARRY
ELECTRICAL-Rough 4/11/2022 Not Ready for Inspection STUART CHAPMAN
HVAC-Rough 4/11/2022 Corrections Issued STUART CHAPMAN
PLUMBING-Rough 4/11/2022 Approved STUART CHAPMAN
Sewer 4/11/2022 Partial Approval STUART CHAPMAN
Wood Frame 4/11/2022 Partial Approval STUART CHAPMAN
ELECTRICAL-Final 4/15/2022 Not Ready for Inspection JUSTIN CURTIS
ELECTRICAL-Rough 4/21/2022 Approved ADAM ESCOTO
Service/Power Release 4/21/2022 Not Ready for Inspection ADAM ESCOTO
HVAC-Rough 5/26/2022 Approved JOSEPH MCGARRY
Insulation 5/26/2022 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 5/26/2022 Partial Approval JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 6/7/2022 SGSOV Not Ready ALIZAH MAYAGOITIA
Final 6/13/2022 Corrections Issued JOSEPH MCGARRY
Gas Test 6/13/2022 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 11/29/2022 SGSOV Not Ready MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 1/31/2023 SGSOV Not Ready MICHAEL LEWIS
Final 6/14/2023 Not Ready for Inspection LILIANA PORTILLO
Green Building Final 6/14/2023 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 6/14/2023 SGSOV Not Ready LILIANA PORTILLO
Smoke Detectors 6/14/2023 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 7/24/2023 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 7/24/2023 Partial Approval ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 7/24/2023 SGSOV Approved ALIZAH MAYAGOITIA
Final 8/31/2023 Corrections Issued LILIANA PORTILLO
Green Building Final 8/31/2023 Corrections Issued LILIANA PORTILLO
HVAC-Final 8/31/2023 Corrections Issued LILIANA PORTILLO
PLUMBING-Final 8/31/2023 Approved LILIANA PORTILLO
Smoke Detectors 8/31/2023 Approved LILIANA PORTILLO
Final 9/13/2023 OK to Issue CofO LILIANA PORTILLO
Green Building Final 9/13/2023 Approved LILIANA PORTILLO
HVAC-Final 9/13/2023 Approved LILIANA PORTILLO