815 S SHERBOURNE DR 90035
Certificate Information: 815 S SHERBOURNE DR 90035
- Application / Permit
- 21016-10000-29698
- Plan Check / Job No.
- B21LA17171
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: Mandatory soft-story retrofit including (1) cantilever column W8x67 and (1) Wood shear wall.
- Permit Issued
- Issued on 1/12/2022
- Issuing Office
- Current Status
- CofC Issued on 5/2/2022
Permit Application Status History
| Submitted | 9/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/21/2021 | JESSE VIDUYA |
| Corrections Issued | 10/28/2021 | JESSE VIDUYA |
| Quality Review Completed | 11/2/2021 | HANS SANTIAGO |
| Plan Check Approved | 11/30/2021 | JESSE VIDUYA |
| Issued | 1/12/2022 | APPLICANT |
| OK for CofC | 4/29/2022 | DARRYL ARNOLD |
| CofC Issued | 5/2/2022 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 1/3/2022 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Cal Retrofit; Lic. No.: 1022167-B | 19528 VENTURA BLVD #300 TARZANA, CA 91356 |
| Engineer | Zohrevand,, Pedram; Lic. No.: C82328 | 19562 VENTURA BLVD UNIT 238 TARZANA, CA 91356 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/26/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Other (see comments) | 3/1/2022 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 3/10/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 3/11/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Other (see comments) | 3/17/2022 | No Access for Inspection | BRUCE CAMPBELL |
| Wood Frame | 3/25/2022 | Approved | DARRYL ARNOLD |
| Wood Frame | 4/4/2022 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 4/13/2022 | Approved | DARRYL ARNOLD |
| Final | 4/29/2022 | OK for CofC | DARRYL ARNOLD |
| METHANE-Final | 4/29/2022 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 4/29/2022 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 4/29/2022 | Approved | DARRYL ARNOLD |