1821 N ALEXANDRIA AVE 90027
Certificate Information: 1821 N ALEXANDRIA AVE 90027
- Application / Permit
- 21016-10000-29147
- Plan Check / Job No.
- B21LA17116
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93. INSTALL 2 Ordinary Moment Frames & ONE Special Cantilever Column
- Permit Issued
- Issued on 5/16/2022
- Issuing Office
- Metro
- Current Status
- CofC Issued on 2/11/2026
Permit Application Status History
| Submitted | 9/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/14/2021 | JESSE VIDUYA |
| Corrections Issued | 10/21/2021 | JESSE VIDUYA |
| Quality Review Completed | 10/26/2021 | HANS SANTIAGO |
| Applicant returned to address corrections | 1/26/2022 | JESSE VIDUYA |
| Plan Check Approved | 3/14/2022 | JESSE VIDUYA |
| Issued | 5/16/2022 | APPLICANT |
| OK for CofC | 2/10/2026 | DARRYL ARNOLD |
| CofC Issued | 2/11/2026 | RAFAEL ESPINOZA |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 4/26/2022 | MICHAEL SOTO |
Contact Information
| Architect | Miller,, Michael; Lic. No.: C26956 | 12756 MITCHELL AVE LOS ANGELES, CA 90066 |
| Contractor | K N D Construction Inc; Lic. No.: 969756-B | 145 S GLENOAKS BLVD #204 BURBANK, CA 91502 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/16/2022 | Approved | BRUCE CAMPBELL |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2022 | Approved | BRUCE CAMPBELL |
| Wood Frame | 6/28/2022 | Partial Approval | BRUCE CAMPBELL |
| Deputy Steel/Welding | 6/29/2022 | Conditional Approval | BRUCE CAMPBELL |
| Deputy Steel/Welding | 6/30/2022 | Conditional Approval | BRUCE CAMPBELL |
| Deputy Wood Construction | 6/30/2022 | Conditional Approval | BRUCE CAMPBELL |
| Deputy Steel/Welding | 7/5/2022 | Conditional Approval | BRUCE CAMPBELL |
| Deputy Steel/Welding | 7/6/2022 | Conditional Approval | BRUCE CAMPBELL |
| Deputy Steel/Welding | 7/15/2022 | Conditional Approval | BRUCE CAMPBELL |
| Deputy Drilled-In Anchors | 7/20/2022 | Conditional Approval | BRUCE CAMPBELL |
| Deputy Steel/Welding | 7/20/2022 | Conditional Approval | BRUCE CAMPBELL |
| Deputy Reinf. Concrete | 7/21/2022 | Conditional Approval | DARRYL ARNOLD |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2022 | Approved | JONATHAN QUACH |
| Footing/Foundation/Slab | 7/22/2022 | Approved | JONATHAN QUACH |
| Structural Steel Frame | 7/22/2022 | Approved | JONATHAN QUACH |
| Wood Frame | 7/22/2022 | Approved | JONATHAN QUACH |
| Deputy Reinf. Concrete | 7/27/2022 | Conditional Approval | WINSTON DUNNING |
| Drywall Nailing | 8/3/2022 | Approved | BRUCE CAMPBELL |
| Interior/Exterior Lathing | 8/3/2022 | Partial Approval | BRUCE CAMPBELL |
| Interior/Exterior Lathing | 8/5/2022 | Approved | BRUCE CAMPBELL |
| Final | 10/12/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 10/12/2022 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 10/12/2022 | Corrections Issued | DARRYL ARNOLD |
| Final | 2/10/2026 | OK for CofC | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 2/10/2026 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 2/10/2026 | Approved | DARRYL ARNOLD |