840 S HILGARD AVE 90024
Certificate Information: 840 S HILGARD AVE 90024
- Application / Permit
- 21016-10000-28997
- Plan Check / Job No.
- B21LA17074
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (5) Apartment
- Work Description
- INTERIOR REMODEL OF EXISTING HOTEL/APARTMENT BUILDING. NO CHANGE OF USE, NO EXTERIOR WORK.
- Permit Issued
- Issued on 1/21/2022
- Issuing Office
- Current Status
- Permit Finaled on 8/12/2024
Permit Application Status History
| Submitted | 9/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/14/2021 | ERIC WONG |
| Corrections Issued | 10/20/2021 | ERIC WONG |
| Quality Review Completed | 10/21/2021 | PETER KIM |
| Disabled Access Plans Picked Up | 10/25/2021 | APPLICANT |
| Building Plans Picked Up | 11/9/2021 | APPLICANT |
| Plan Check Approved | 1/19/2022 | ERIC WONG |
| Issued | 1/21/2022 | APPLICANT |
| Permit Finaled | 8/7/2024 | PAUL DAVIDSON |
Permit Application Clearance Information
| Sewer availability | Cleared | 10/26/2021 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 10/27/2021 | HISASHI KOBAYAKAWA |
| "Q" conditions | Cleared | 10/29/2021 | KEVIN FULTON |
| Specific Plan | Cleared | 10/29/2021 | KEVIN FULTON |
| Specific Plan | Cleared | 10/29/2021 | KEVIN FULTON |
| ZI | Cleared | 10/29/2021 | KEVIN FULTON |
| ZI | Cleared | 10/29/2021 | KEVIN FULTON |
| Fire Marshal Fire Life Safety | Cleared | 12/22/2021 | VIDAL GARCIA |
| DAS Clearance | Cleared | 12/27/2021 | SHINE LIN |
Contact Information
| Architect | Zbikowski,, Jeffrey; Lic. No.: C35389 | 1810 14TH STREET SUITE 204 SANTA MONICA, CA 90404 |
| Contractor | Owner-Builder | , |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/11/2022 | Approved | GRANT WOODS |
| Interior/Exterior Lathing | 5/11/2022 | Not Ready for Inspection | PAUL DAVIDSON |
| Interior/Exterior Lathing | 5/13/2022 | Corrections Issued | GRANT WOODS |
| Wood Frame | 5/16/2022 | Partial Approval | PAUL DAVIDSON |
| Drywall Nailing | 5/19/2022 | Partial Approval | PAUL DAVIDSON |
| Wood Frame | 5/19/2022 | Approved | PAUL DAVIDSON |
| Drywall Nailing | 5/24/2022 | Approved | PAUL DAVIDSON |
| Final | 6/10/2022 | Not Ready for Inspection | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 6/10/2022 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 6/10/2022 | Approved | GRANT WOODS |
| Final | 4/12/2024 | Not Ready for Inspection | DERRICK SPENCER |
| Final | 4/18/2024 | Not Ready for Inspection | RICARDO ROBLES |
| Final | 8/7/2024 | Permit Finaled | PAUL DAVIDSON |