1043 S VICTORIA AVE 90019
Certificate Information: 1043 S VICTORIA AVE 90019
- Application / Permit
- 21016-10000-28985
- Plan Check / Job No.
- B21LA17071
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior remodel of existing single family dwelling, replace windows
- Permit Issued
- Issued on 12/1/2021
- Issuing Office
- Current Status
- Permit Finaled on 4/22/2022
Permit Application Status History
| Submitted | 9/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/16/2021 | SHANGQIN XIE |
| Corrections Issued | 9/16/2021 | SHANGQIN XIE |
| Applicant returned to address corrections | 11/15/2021 | AUNG SOE |
| Plan Check Approved | 11/17/2021 | AUNG SOE |
| Issued | 12/1/2021 | APPLICANT |
| Building Plans Picked Up | 12/7/2021 | APPLICANT |
| Permit Finaled | 4/21/2022 | SHAVONNE ESPINOZA |
Permit Application Clearance Information
| HPOZ | Cleared | 10/18/2021 | AMANDA KAINER |
| Sewer availability | Cleared | 10/22/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 10/26/2021 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hwang,, Junho; Lic. No.: S5592 | 815 FAIRVIEW AVE #205 SOUTH PASADENA, CA 91030 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/10/2022 | Conditional Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 1/10/2022 | Conditional Approval | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 1/19/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| Wood Frame | 1/25/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| BUILDING-Rough-Frame | 1/26/2022 | Partial Approval | CRAIG DAVIS |
| BUILDING-Rough-Frame | 2/15/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Insulation | 2/15/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 2/22/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| BUILDING-Rough-Frame | 2/28/2022 | Partial Approval | SHAVONNE ESPINOZA |
| HVAC-Rough | 2/28/2022 | Approved | SHAVONNE ESPINOZA |
| Insulation | 2/28/2022 | Partial Approval | SHAVONNE ESPINOZA |
| Drywall Nailing | 3/2/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Drywall Nailing | 3/4/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Shower Pan | 3/7/2022 | Partial Approval | SHAVONNE ESPINOZA |
| Insulation | 3/9/2022 | Approved | SHAVONNE ESPINOZA |
| Shower Pan | 3/9/2022 | Approved | SHAVONNE ESPINOZA |
| ELECTRICAL-Final | 3/29/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Final | 3/29/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| HVAC-Final | 3/29/2022 | Approved | SHAVONNE ESPINOZA |
| PLUMBING-Final | 3/29/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 3/29/2022 | SGSOV Approved | SHAVONNE ESPINOZA |
| Smoke Detectors | 3/29/2022 | Approved | SHAVONNE ESPINOZA |
| ELECTRICAL-Final | 4/21/2022 | Approved | SHAVONNE ESPINOZA |
| Final | 4/21/2022 | Permit Finaled | SHAVONNE ESPINOZA |
| HVAC-Final | 4/21/2022 | Approved | SHAVONNE ESPINOZA |
| PLUMBING-Final | 4/21/2022 | Approved | SHAVONNE ESPINOZA |