8113 W MANCHESTER AVE 90293

Certificate Information: 8113 W MANCHESTER AVE 90293

Application / Permit
21016-10000-27633
Plan Check / Job No.
B21LA16965
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Massage Parlor
Work Description
Change of use from beauty parlor to massage parlor where any person who provides massage services at this premise shall be certified as a massage therapist or massage practitioner pursuant to California Business and Profession Section 4600 et seq. Work to inlcude new partitions, add accessible restroom, and finishes.
Permit Issued
Issued on 2/16/2022
Issuing Office
Current Status
CofO Issued on 5/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/16/2021 APPLICANT
Assigned to Plan Check Engineer 9/17/2021 SAMUEL GONZALEZ
Corrections Issued 9/18/2021 SAMUEL GONZALEZ
Applicant returned to address corrections 9/30/2021 ZAW HAN
Applicant returned to address corrections 12/28/2021 FERNANDO FLORES
Plan Check Approved 2/15/2022 FERNANDO FLORES
Issued 2/16/2022 APPLICANT
Building Plans Picked Up 3/2/2022 APPLICANT
CofO in Progress 5/16/2022 GRANT WOODS
Permit Finaled 5/16/2022 DAVID TSAU
CofO Issued 5/16/2022 DAVID TSAU
Permit Finaled 5/16/2022 DAVID TSAU

Permit Application Clearance Information

ZA Case Cleared 10/22/2021 JASON CHAN
ZA Case Cleared 10/22/2021 JASON CHAN
ZA Case Cleared 10/22/2021 JASON CHAN
Specific Plan Cleared 11/29/2021 FREDDY GARCIA
Eng Process Fee Ord 176,300 Cleared 12/3/2021 ANTHONY MAINEZ
Sewer availability Cleared 12/3/2021 ANTHONY MAINEZ

Contact Information

Contractor Mas Real Construction Inc; Lic. No.: 1019179-B 3920 BOYCE AVENUE      LOS ANGELES, CA 90039

Inspector Information

DANIEL ARMENTA, (310) 914-3925 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/8/2022 Corrections Issued GRANT WOODS
Light Gage Steel Frame 3/16/2022 Not Ready for Inspection GRANT WOODS
Excavation/Setback/Form/Re-Bar 3/18/2022 Corrections Issued JOEY BUCHANAN
Light Gage Steel Frame 3/18/2022 Approved JOEY BUCHANAN
Final 5/2/2022 Conditional Approval JOEY BUCHANAN
METHANE-Final 5/2/2022 Approved JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 5/2/2022 SGSOV Approved JOEY BUCHANAN
Smoke Detectors 5/2/2022 Approved JOEY BUCHANAN
Final 5/13/2022 Conditional Approval GRANT WOODS