816 3/4 E 87TH PL 90002
Certificate Information: 816 3/4 E 87TH PL 90002
- Application / Permit
- 21016-10000-27455
- Plan Check / Job No.
- B21LA16911
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT ATTACHED GARAGE OF AN (E) DUPLEX TO AN ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(C). 2 OF 2
- Permit Issued
- Issued on 9/11/2023
- Issuing Office
- Current Status
- CofO Issued on 12/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/14/2021 | KEVIN MORALES |
| Corrections Issued | 10/20/2021 | KEVIN MORALES |
| Quality Review Completed | 10/25/2021 | EUGENE BARBEAU |
| Building Plans Picked Up | 10/28/2021 | APPLICANT |
| Plan Check Approved | 9/11/2023 | KEVIN MORALES |
| Issued | 9/11/2023 | APPLICANT |
| CofO in Progress | 12/23/2025 | JOHN QUINTANILLA |
| Permit Finaled | 12/23/2025 | DEROLD HAUFF |
| CofO Issued | 12/23/2025 | DEROLD HAUFF |
| Permit Finaled | 12/23/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/10/2021 | KHOUNG LE |
| Sewer availability | Cleared | 11/10/2021 | KHOUNG LE |
| Eng Process Fee Ord 176,300 | Cleared | 11/16/2021 | KHOUNG LE |
| Construction near power lines | Cleared | 9/1/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Jarh Builders Corporation; Lic. No.: 1074687-B | 15740 PARAMOUNT BLVD #E PARAMOUNT, CA 90723 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 10/1/2024 | Corrections Issued | LUIS CASTRO |
| Underground Mechanical | 10/2/2024 | Approved | JOHN QUINTANILLA |
| Deputy Drilled-In Anchors | 11/27/2024 | Conditional Approval | ALEX COLIN |
| Deputy Drilled-In Anchors | 12/4/2024 | Conditional Approval | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 12/18/2024 | Not Ready for Inspection | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 12/18/2024 | Not Ready for Inspection | JOHN QUINTANILLA |
| Green Building Rough | 12/18/2024 | Not Ready for Inspection | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 1/7/2025 | Approved | JOHN QUINTANILLA |
| Excavation/Setback/Form/Re-Bar | 1/24/2025 | Partial Inspection | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 1/24/2025 | Partial Approval | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 3/6/2025 | Partial Approval | JOHN QUINTANILLA |
| Green Building Rough | 3/6/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Rough-Elec/Plmb/HVAC | 3/6/2025 | Approved | JOHN QUINTANILLA |
| Deputy Wood Construction | 3/20/2025 | Conditional Approval | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 4/24/2025 | Corrections Issued | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Green Building Rough | 4/24/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 4/30/2025 | Corrections Issued | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 4/30/2025 | Corrections Issued | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 5/12/2025 | Approved | JOHN QUINTANILLA |
| Green Building Rough | 5/12/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Insulation | 5/19/2025 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 7/9/2025 | Approved | JOHN QUINTANILLA |
| Green Building Rough | 7/9/2025 | Approved | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 7/9/2025 | Partial Approval | JOHN QUINTANILLA |
| Final | 11/25/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Green Building Final | 11/25/2025 | Approved | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 11/25/2025 | SGSOV Not Required | JOHN QUINTANILLA |
| Smoke Detectors | 11/25/2025 | Approved | JOHN QUINTANILLA |
| Final | 12/2/2025 | OK to Issue CofO | JOHN QUINTANILLA |