486 W AVENUE 44 90065

Certificate Information: 486 W AVENUE 44 90065

Application / Permit
21016-10000-27422
Plan Check / Job No.
B21LA16908
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL BOTH FLOORS OF (E) SFD. INCLUDES DOOR AND WINDOW RE-WORK AND NEW STRUCTURAL FRAMING.
Permit Issued
Issued on 4/8/2022
Issuing Office
Current Status
Permit Finaled on 3/7/2023

Permit Application Status History

Submitted 9/10/2021 APPLICANT
Assigned to Plan Check Engineer 9/14/2021 LAWRENCE QUIRANTE
Corrections Issued 9/14/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 9/27/2021 STANLEY RAAP
Plan Check Approved 9/28/2021 STANLEY RAAP
Issued 4/8/2022 APPLICANT
Building Plans Picked Up 4/8/2022 APPLICANT
Permit Finaled 3/6/2023 OSVALDO PARAMO

Permit Application Clearance Information

Specific Plan Cleared 9/23/2021 ANNA VIDAL

Contact Information

Contractor Redraw Inc; Lic. No.: 1067872-B 15340 TEXACO AVE      PARAMOUNT, CA 90723
Engineer Garza,, Omar Leonel; Lic. No.: S5593 600 WILSHIRE BLVD 760      LOS ANGELES, CA 90017

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/20/2022 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 8/12/2022 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Rough 8/12/2022 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Rough 8/17/2022 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 8/17/2022 Approved OSVALDO PARAMO
PLUMBING-Rough 8/17/2022 Approved OSVALDO PARAMO
Shower Pan 9/19/2022 Approved ALIZAH MAYAGOITIA
HVAC-Rough 9/21/2022 Partial Approval OSVALDO PARAMO
HVAC-Rough 9/23/2022 Approved OSVALDO PARAMO
Interior/Exterior Lathing 9/23/2022 Partial Approval OSVALDO PARAMO
Interior/Exterior Lathing 9/26/2022 Not Ready for Inspection OSVALDO PARAMO
Interior/Exterior Lathing 10/7/2022 Partial Approval SCOTT FINNILA
Interior/Exterior Lathing 10/12/2022 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 10/19/2022 Approved OSVALDO PARAMO
Insulation 11/2/2022 Approved OSVALDO PARAMO
Drywall Nailing 11/15/2022 Approved ALIZAH MAYAGOITIA
Service/Power Release 1/27/2023 Approved SCOTT FINNILA
Final 2/27/2023 Corrections Issued ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 2/27/2023 SGSOV Not Ready ALIZAH MAYAGOITIA
Smoke Detectors 2/27/2023 Approved ALIZAH MAYAGOITIA
Final 3/6/2023 Permit Finaled OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 3/6/2023 SGSOV Approved OSVALDO PARAMO