6424 N FALLBROOK AVE 91307
Certificate Information: 6424 N FALLBROOK AVE 91307
- Application / Permit
- 21016-10000-25919
- Plan Check / Job No.
- B21LA16873
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Furniture Store
- Work Description
- Change of Use from Retail to Furniture Retail. No change in Occupancy and Parking.
- Permit Issued
- Issued on 11/30/2021
- Issuing Office
- Current Status
- CofO Issued on 7/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/16/2021 | SHANGQIN XIE |
| Corrections Issued | 9/16/2021 | SHANGQIN XIE |
| Applicant returned to address corrections | 11/4/2021 | ZAW HAN |
| Plan Check Approved | 11/9/2021 | ZAW HAN |
| Issued | 11/30/2021 | APPLICANT |
| Building Plans Picked Up | 11/30/2021 | APPLICANT |
| CofO in Progress | 7/13/2022 | JEFFREY DURAN |
| CofO Issued | 7/14/2022 | JEFFREY DURAN |
| Permit Finaled | 7/14/2022 | JEFFREY DURAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/21/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 9/21/2021 | DAGOVERTO GUERRERO |
| Miscellaneous | Cleared | 9/24/2021 | KENTON TRINH |
| ZA Case | Cleared | 9/24/2021 | KENTON TRINH |
| ZA Case | Cleared | 9/24/2021 | KENTON TRINH |
| ZA Case | Cleared | 9/24/2021 | KENTON TRINH |
Contact Information
| Architect | Steele,, William Robert; Lic. No.: C25712 | 2529 TALMADGE ROAD TOLEDO, OH 43606 |
| Contractor | Bogart Construction Inc; Lic. No.: 707471-B | 9980 IRVINE CENTER DRIVE #200 IRVINE, CA 92618 |
| Engineer | Fontaine,, Eric Stuart; Lic. No.: S5930 | 870 ANTILLA WAY SAN MARCOS, CA 92078 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Reinforced Masonry Frame | 12/29/2021 | Partial Inspection | ANDREW DORSO |
| Masonry Wall/Backfill | 1/4/2022 | Partial Approval | DANIEL VARNUM |
| Structural Steel Frame | 1/4/2022 | Partial Approval | DANIEL VARNUM |
| Deputy Drilled-In Anchors | 1/19/2022 | Conditional Approval | ANDREW DORSO |
| Deputy Reinf. Concrete | 1/19/2022 | Conditional Approval | ANDREW DORSO |
| Excavation/Setback/Form/Re-Bar | 1/19/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 1/19/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Reinforced Concrete Frame | 1/19/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 1/21/2022 | Partial Approval | CAMERON CHABAN |
| Footing/Foundation/Slab | 1/21/2022 | Partial Approval | CAMERON CHABAN |
| Wood Frame | 1/24/2022 | Conditional Approval | CAMERON CHABAN |
| Deputy Steel/Welding | 1/26/2022 | Conditional Approval | JEFFREY DURAN |
| Light Gage Steel Frame | 1/26/2022 | Partial Approval | CAMERON CHABAN |
| Deputy Steel/Welding | 1/27/2022 | No Result Entered | GARY EWELL |
| Excavation/Setback/Form/Re-Bar | 1/27/2022 | Approved | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2022 | Approved | DANIEL VARNUM |
| Wood Frame | 1/27/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Wood Frame | 2/1/2022 | Partial Approval | DANIEL VARNUM |
| Light Gage Steel Frame | 2/7/2022 | Partial Approval | DANIEL VARNUM |
| Drywall Nailing | 2/14/2022 | Partial Approval | CAMERON CHABAN |
| Deputy Steel/Welding | 2/17/2022 | Conditional Approval | CAMERON CHABAN |
| Drywall Nailing | 2/17/2022 | Approved | DANIEL VARNUM |
| Deputy Steel/Welding | 3/1/2022 | Conditional Approval | CAMERON CHABAN |
| Excavation/Setback/Form/Re-Bar | 3/1/2022 | Conditional Approval | CAMERON CHABAN |
| Structural Steel Frame | 3/1/2022 | Not Ready for Inspection | CAMERON CHABAN |
| Drywall Nailing | 3/10/2022 | Partial Approval | CAMERON CHABAN |
| Footing/Foundation/Slab | 3/15/2022 | Approved | DANIEL VARNUM |
| Reinforced Concrete Frame | 3/15/2022 | No Access for Inspection | DANIEL VARNUM |
| Drywall Nailing | 3/30/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Interior/Exterior Lathing | 3/30/2022 | Partial Approval | DANIEL VARNUM |
| Interior/Exterior Lathing | 4/7/2022 | Approved | DANIEL VARNUM |
| Deputy Steel/Welding | 4/29/2022 | Conditional Approval | JEFFREY DURAN |
| Final | 5/23/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Green Building Final | 5/23/2022 | Not Ready for Inspection | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 5/23/2022 | SGSOV Not Ready | DANIEL VARNUM |
| Smoke Detectors | 5/23/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Final | 6/2/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Green Building Final | 6/2/2022 | Not Ready for Inspection | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 6/2/2022 | SGSOV Not Ready | DANIEL VARNUM |
| Smoke Detectors | 6/2/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Final | 6/9/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Green Building Final | 6/9/2022 | Not Ready for Inspection | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 6/9/2022 | SGSOV No Gas | DANIEL VARNUM |
| Smoke Detectors | 6/9/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Final | 6/23/2022 | Partial Inspection | DANIEL VARNUM |
| Green Building Final | 6/23/2022 | Approved | DANIEL VARNUM |
| Smoke Detectors | 6/23/2022 | Approved | DANIEL VARNUM |
| Final | 7/13/2022 | OK to Issue CofO | JEFFREY DURAN |