6424 N FALLBROOK AVE 91307

Certificate Information: 6424 N FALLBROOK AVE 91307

Application / Permit
21016-10000-25919
Plan Check / Job No.
B21LA16873
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Furniture Store
Work Description
Change of Use from Retail to Furniture Retail. No change in Occupancy and Parking.
Permit Issued
Issued on 11/30/2021
Issuing Office
Current Status
CofO Issued on 7/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/13/2021 APPLICANT
Assigned to Plan Check Engineer 9/16/2021 SHANGQIN XIE
Corrections Issued 9/16/2021 SHANGQIN XIE
Applicant returned to address corrections 11/4/2021 ZAW HAN
Plan Check Approved 11/9/2021 ZAW HAN
Issued 11/30/2021 APPLICANT
Building Plans Picked Up 11/30/2021 APPLICANT
CofO in Progress 7/13/2022 JEFFREY DURAN
CofO Issued 7/14/2022 JEFFREY DURAN
Permit Finaled 7/14/2022 JEFFREY DURAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/21/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 9/21/2021 DAGOVERTO GUERRERO
Miscellaneous Cleared 9/24/2021 KENTON TRINH
ZA Case Cleared 9/24/2021 KENTON TRINH
ZA Case Cleared 9/24/2021 KENTON TRINH
ZA Case Cleared 9/24/2021 KENTON TRINH

Contact Information

Architect Steele,, William Robert; Lic. No.: C25712 2529 TALMADGE ROAD      TOLEDO, OH 43606
Contractor Bogart Construction Inc; Lic. No.: 707471-B 9980 IRVINE CENTER DRIVE #200      IRVINE, CA 92618
Engineer Fontaine,, Eric Stuart; Lic. No.: S5930 870 ANTILLA WAY      SAN MARCOS, CA 92078

Inspector Information

BRIAN KELLY, (818) 374-1127 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Reinforced Masonry Frame 12/29/2021 Partial Inspection ANDREW DORSO
Masonry Wall/Backfill 1/4/2022 Partial Approval DANIEL VARNUM
Structural Steel Frame 1/4/2022 Partial Approval DANIEL VARNUM
Deputy Drilled-In Anchors 1/19/2022 Conditional Approval ANDREW DORSO
Deputy Reinf. Concrete 1/19/2022 Conditional Approval ANDREW DORSO
Excavation/Setback/Form/Re-Bar 1/19/2022 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 1/19/2022 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 1/19/2022 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 1/21/2022 Partial Approval CAMERON CHABAN
Footing/Foundation/Slab 1/21/2022 Partial Approval CAMERON CHABAN
Wood Frame 1/24/2022 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 1/26/2022 Conditional Approval JEFFREY DURAN
Light Gage Steel Frame 1/26/2022 Partial Approval CAMERON CHABAN
Deputy Steel/Welding 1/27/2022 No Result Entered GARY EWELL
Excavation/Setback/Form/Re-Bar 1/27/2022 Approved DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 1/27/2022 Approved DANIEL VARNUM
Wood Frame 1/27/2022 Not Ready for Inspection DANIEL VARNUM
Wood Frame 2/1/2022 Partial Approval DANIEL VARNUM
Light Gage Steel Frame 2/7/2022 Partial Approval DANIEL VARNUM
Drywall Nailing 2/14/2022 Partial Approval CAMERON CHABAN
Deputy Steel/Welding 2/17/2022 Conditional Approval CAMERON CHABAN
Drywall Nailing 2/17/2022 Approved DANIEL VARNUM
Deputy Steel/Welding 3/1/2022 Conditional Approval CAMERON CHABAN
Excavation/Setback/Form/Re-Bar 3/1/2022 Conditional Approval CAMERON CHABAN
Structural Steel Frame 3/1/2022 Not Ready for Inspection CAMERON CHABAN
Drywall Nailing 3/10/2022 Partial Approval CAMERON CHABAN
Footing/Foundation/Slab 3/15/2022 Approved DANIEL VARNUM
Reinforced Concrete Frame 3/15/2022 No Access for Inspection DANIEL VARNUM
Drywall Nailing 3/30/2022 Not Ready for Inspection DANIEL VARNUM
Interior/Exterior Lathing 3/30/2022 Partial Approval DANIEL VARNUM
Interior/Exterior Lathing 4/7/2022 Approved DANIEL VARNUM
Deputy Steel/Welding 4/29/2022 Conditional Approval JEFFREY DURAN
Final 5/23/2022 Not Ready for Inspection DANIEL VARNUM
Green Building Final 5/23/2022 Not Ready for Inspection DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 5/23/2022 SGSOV Not Ready DANIEL VARNUM
Smoke Detectors 5/23/2022 Not Ready for Inspection DANIEL VARNUM
Final 6/2/2022 Not Ready for Inspection DANIEL VARNUM
Green Building Final 6/2/2022 Not Ready for Inspection DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 6/2/2022 SGSOV Not Ready DANIEL VARNUM
Smoke Detectors 6/2/2022 Not Ready for Inspection DANIEL VARNUM
Final 6/9/2022 Not Ready for Inspection DANIEL VARNUM
Green Building Final 6/9/2022 Not Ready for Inspection DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 6/9/2022 SGSOV No Gas DANIEL VARNUM
Smoke Detectors 6/9/2022 Not Ready for Inspection DANIEL VARNUM
Final 6/23/2022 Partial Inspection DANIEL VARNUM
Green Building Final 6/23/2022 Approved DANIEL VARNUM
Smoke Detectors 6/23/2022 Approved DANIEL VARNUM
Final 7/13/2022 OK to Issue CofO JEFFREY DURAN