6083-6083 1/2 E YORK BLVD 90042
Certificate Information: 6083-6083 1/2 E YORK BLVD 90042
- Application / Permit
- 21016-10000-25867
- Plan Check / Job No.
- B21LA16827
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSE CONVERION OF A PORTION OF SFD TO AN ATTACHED 487 SF ADU.
- Permit Issued
- Issued on 1/23/2022
- Issuing Office
- Current Status
- CofO Issued on 6/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/14/2021 | JOSEPH RAFOLS |
| Corrections Issued | 9/14/2021 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 11/2/2021 | DANIEL SANJUAN |
| Applicant returned to address corrections | 12/7/2021 | JOSEPH RAFOLS |
| Building Plans Picked Up | 1/5/2022 | APPLICANT |
| Applicant returned to address corrections | 1/12/2022 | ZAW HAN |
| Plan Check Approved | 1/18/2022 | ZAW HAN |
| Issued | 1/23/2022 | APPLICANT |
| CofO in Progress | 5/31/2022 | CRAIG VAUGHAN |
| CofO in Progress | 5/31/2022 | CRAIG VAUGHAN |
| Permit Finaled | 6/28/2022 | DEROLD HAUFF |
| CofO Issued | 6/28/2022 | DEROLD HAUFF |
| Permit Finaled | 6/28/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/14/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 11/23/2021 | JEANIE LAM |
| "Q" conditions | Cleared | 1/7/2022 | RICHARD REASER |
| Sewer availability | Cleared | 1/10/2022 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/22/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 4/28/2022 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 4/28/2022 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 5/17/2022 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 5/17/2022 | SGSOV Not Ready | CRAIG VAUGHAN |
| Final | 5/19/2022 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 5/19/2022 | SGSOV Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 5/23/2022 | Approved | ALIZAH MAYAGOITIA |
| Final | 5/23/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 5/23/2022 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 5/23/2022 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 5/23/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 5/23/2022 | Approved | ALIZAH MAYAGOITIA |
| Final | 5/25/2022 | OK to Issue CofO | CRAIG VAUGHAN |
| HVAC-Final | 5/25/2022 | Approved | CRAIG VAUGHAN |