10558 W FONTENELLE WAY 90077
Certificate Information: 10558 W FONTENELLE WAY 90077
- Application / Permit
- 21016-10000-25863
- Plan Check / Job No.
- B21LA16826
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1) UPDATE 2 EXISTING DOOR OPENINGS WITH NEW POCKET PATIO DOORS, FURR OUT NON-LOAD BEARING WALLS TO ALLOW FOR POCKET RECESS. (NO HEADER OR OPENING CHANGE) 2) INSTALL A NEW BAY WINDOW OVER AREA OF EXISTING WINDOWS, REMOVE WINDOWS TO ALLOW PASS-THRU FOR NEW BAY WINDOW. (NO HEADER OR OPENING CHANGE) 3) REPLACE 1-EXISTING DOOR AND 1 WINDOW WITH LIKE FOR LIKE.
- Permit Issued
- Issued on 12/22/2021
- Issuing Office
- Current Status
- Issued on 12/22/2021
Permit Application Status History
| Submitted | 9/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/10/2021 | DANIEL SANJUAN |
| Corrections Issued | 9/13/2021 | DANIEL SANJUAN |
| Applicant returned to address corrections | 10/28/2021 | SINA KHOSRAVI |
| Applicant returned to address corrections | 12/1/2021 | SHANGQIN XIE |
| Issued | 12/22/2021 | APPLICANT |
| Building Plans Picked Up | 1/3/2022 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/19/2021 | MATTHEW JENKINS |
Contact Information
| Contractor | Casey'S Custom Construction; Lic. No.: 553222-B | 5169 OCEAN VIEW BLVD LA CANADA, CA 91011 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Interior/Exterior Lathing | 5/27/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Pre-Inspection | 10/18/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Pre-Inspection | 10/21/2022 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 11/4/2022 | Approved | CHRISTOPHER WILSON |
| Wood Frame | 11/4/2022 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 11/21/2022 | Corrections Issued | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 12/6/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Final | 1/3/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 1/3/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 1/3/2023 | SGSOV Not Ready | GERMAN RODRIGUEZ MENDOZA |
| Smoke Detectors | 1/3/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |