417 E 7TH ST 90014

Certificate Information: 417 E 7TH ST 90014

Application / Permit
21016-10000-25745
Plan Check / Job No.
B21LA16752
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
CHANGE OF USE FROM WAREHOUSE TO MARKET
Permit Issued
Issued on 2/8/2022
Issuing Office
Current Status
Issued on 2/8/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/8/2021 APPLICANT
Assigned to Plan Check Engineer 9/23/2021 SERGIO GUTIERREZ
Corrections Issued 9/29/2021 SERGIO GUTIERREZ
Quality Review Completed 10/1/2021 FARUK SEZER
Disabled Access Plans Picked Up 11/5/2021 APPLICANT
Applicant returned to address corrections 11/19/2021 SERGIO GUTIERREZ
Plan Check Approved 11/24/2021 SERGIO GUTIERREZ
Building Plans Picked Up 12/8/2021 APPLICANT
Issued 2/8/2022 APPLICANT

Permit Application Clearance Information

"Q" conditions Cleared 10/12/2021 RICHARD REASER
CPC Cleared 10/12/2021 RICHARD REASER
Comm Cor/Mini-Mall Cleared 10/12/2021 RICHARD REASER
Miscellaneous Cleared 10/12/2021 RICHARD REASER
Historic Resource Verification Cleared 10/14/2021 MICAELA TORRES-GIL
DAS Clearance Cleared 10/21/2021 SERGIO GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 10/22/2021 CHRISTOPHER ROCHA
Sewer availability Cleared 10/22/2021 CHRISTOPHER ROCHA
Redevelopment Project Area Cleared 10/25/2021 SUSAN WONG
Food Service Establishment Cleared 11/22/2021 JASH PATEL
Food establishment approval Cleared 11/23/2021 LACDHS APPROVED

Contact Information

Architect Moradi, Owrang, Sheida; Lic. No.: C35621 22035 PROVIDENCIA STREET      WOODLAND HILLS, CA 91364
Contractor Builders Firm Inc; Lic. No.: 1015246-B 1617 WEST SHORB STREET      ALHAMBRA, CA 91803

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

SGSOV-Seismic Gas S/O Valve 6/16/2022 SGSOV Not Ready KATY RAMIREZ
Pre-Inspection 6/21/2022 Approved KATY RAMIREZ
Final 10/19/2022 Not Ready for Inspection TIMOTHY BUXTON
Reinforced Masonry Frame 10/19/2022 Approved TIMOTHY BUXTON
SGSOV-Seismic Gas S/O Valve 10/19/2022 SGSOV No Gas TIMOTHY BUXTON
Smoke Detectors 10/19/2022 Approved TIMOTHY BUXTON
Final 1/12/2024 Not Ready for Inspection KATY RAMIREZ
Final 7/18/2025 Not Ready for Inspection JEROME BLACKWOOD
Final 11/10/2025 Partial Approval PAUL BAZERKANIAN