8141 S GULANA AVE 90293
Certificate Information: 8141 S GULANA AVE 90293
- Application / Permit
- 21016-10000-24752
- Plan Check / Job No.
- B21LA16673
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- INTERIOR TENANT IMPROVEMENT INCLUDING: NEW NONSTRUCTURAL INTERIOR PARTITIONS; DOORS; MILLWORK; LIGHTING; FINISHES; EV PARKING STALLS AND STRIPING FOR ACCESSIBLE PARKING STALLS. NO CHANGE IN PARKING COUNT.
- Permit Issued
- Issued on 8/17/2022
- Issuing Office
- Current Status
- Permit Finaled on 7/1/2024
Permit Application Status History
| Submitted | 9/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/8/2021 | JOE VO |
| Corrections Issued | 9/8/2021 | JOE VO |
| Plan Check Approved | 11/10/2021 | JOE VO |
| Plan Check Approved | 5/16/2022 | JOE VO |
| No Progress | 7/25/2022 | JOE VO |
| Plan Check Approved | 7/25/2022 | JOE VO |
| No Progress | 8/10/2022 | JOE VO |
| Plan Check Approved | 8/10/2022 | JOE VO |
| Issued | 8/17/2022 | APPLICANT |
| Permit Finaled | 7/1/2024 | GRANT WOODS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/30/2021 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 9/30/2021 | HISASHI KOBAYAKAWA |
| ZA Case | Cleared | 10/19/2021 | ANACANY HURTADO |
| Specific Plan | Cleared | 10/27/2021 | PETE EYRE |
| Abandoned oil well | Cleared | 1/16/2022 | JOHN CONNEALLY |
Contact Information
| Contractor | Thomco Construction Inc; Lic. No.: 730401-B | 1279 N PATT STREET ANAHEIM, CA 92801 |
Inspector Information
| DANIEL ARMENTA, (310) 914-3925 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/19/2022 | Conditional Approval | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 10/19/2022 | Approved | GRANT WOODS |
| Footing/Foundation/Slab | 10/19/2022 | Partial Approval | GRANT WOODS |
| Deputy Reinf. Concrete | 10/20/2022 | Conditional Approval | GRANT WOODS |
| Deputy Drilled-In Anchors | 10/24/2022 | Conditional Approval | GRANT WOODS |
| Footing/Foundation/Slab | 11/1/2022 | Partial Approval | GRANT WOODS |
| Deputy Reinf. Concrete | 11/3/2022 | Conditional Approval | GRANT WOODS |
| Deputy Drilled-In Anchors | 11/18/2022 | Conditional Approval | GRANT WOODS |
| Deputy Other (see comments) | 11/18/2022 | Conditional Approval | GRANT WOODS |
| Deputy Drilled-In Anchors | 11/28/2022 | Conditional Approval | ALAN NOVAK |
| Deputy Other (see comments) | 11/28/2022 | Conditional Approval | ALAN NOVAK |
| Drywall Nailing | 1/9/2023 | Partial Approval | GRANT WOODS |
| Insulation | 1/9/2023 | Approved | GRANT WOODS |
| Light Gage Steel Frame | 1/9/2023 | Partial Approval | GRANT WOODS |
| Deputy Drilled-In Anchors | 1/18/2023 | Conditional Approval | GRANT WOODS |
| Drywall Nailing | 1/18/2023 | Partial Approval | GRANT WOODS |
| Drywall Nailing | 1/25/2023 | Partial Approval | GRANT WOODS |
| Light Gage Steel Frame | 1/25/2023 | Conditional Approval | GRANT WOODS |
| Structural Steel Frame | 1/25/2023 | Partial Approval | GRANT WOODS |
| Drywall Nailing | 2/22/2023 | Partial Approval | GRANT WOODS |
| Interior/Exterior Lathing | 2/22/2023 | Approved | GRANT WOODS |
| T-Bar Ceiling | 3/31/2023 | Not Ready for Inspection | GRANT WOODS |
| T-Bar Ceiling | 4/5/2023 | Partial Approval | GRANT WOODS |
| Deputy Drilled-In Anchors | 5/26/2023 | Conditional Approval | GRANT WOODS |
| Deputy Reinf. Concrete | 6/6/2023 | Conditional Approval | GRANT WOODS |
| Light Gage Steel Frame | 6/28/2023 | Approved | MICHAEL PETRUSKO |
| Drywall Nailing | 6/30/2023 | Approved | MICHAEL PETRUSKO |
| Special/Order Compliance | 7/18/2023 | Not Ready for Inspection | GRANT WOODS |
| T-Bar Ceiling | 7/18/2023 | Corrections Issued | GRANT WOODS |
| Final | 6/26/2024 | Conditional Approval | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 6/26/2024 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 6/26/2024 | Approved | GRANT WOODS |
| Final | 7/1/2024 | Permit Finaled | GRANT WOODS |