847-849 E 33RD ST 90011
Certificate Information: 847-849 E 33RD ST 90011
- Application / Permit
- 21016-10000-24086
- Plan Check / Job No.
- B21LA16647
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Conversion of attached garage into one story attached ADU per GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 12/8/2021
- Issuing Office
- Current Status
- CofO Issued on 7/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/8/2021 | RAMA DABADGE |
| Corrections Issued | 9/8/2021 | RAMA DABADGE |
| Plan Check Approved | 11/4/2021 | SAMUEL GONZALEZ |
| Issued | 12/8/2021 | APPLICANT |
| Building Plans Picked Up | 12/22/2021 | APPLICANT |
| CofO in Progress | 7/21/2022 | MEL KHACHATOURIAN |
| Permit Finaled | 7/27/2022 | BRUCE TODD |
| CofO Issued | 7/27/2022 | BRUCE TODD |
| Permit Finaled | 7/27/2022 | BRUCE TODD |
Permit Application Clearance Information
| Address approval | Cleared | 9/28/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 9/30/2021 | CELINA MORENO |
| Sewer availability | Cleared | 9/30/2021 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEREMY TODD, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARVIN FONSECA, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GUEVARA, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/25/2022 | Approved | MARIO CUEVAS |
| ELECTRICAL-Rough | 3/11/2022 | Partial Approval | MARIO CUEVAS |
| PLUMBING-Rough | 3/11/2022 | Corrections Issued | MARIO CUEVAS |
| BUILDING-Rough-Frame | 3/25/2022 | Approved | MARIO CUEVAS |
| ELECTRICAL-Rough | 3/25/2022 | Approved | MARIO CUEVAS |
| Green Building Rough | 3/25/2022 | Approved | MARIO CUEVAS |
| PLUMBING-Rough | 3/25/2022 | Approved | MARIO CUEVAS |
| Insulation | 3/30/2022 | Approved | MARIO CUEVAS |
| Interior/Exterior Lathing | 3/30/2022 | Not Ready for Inspection | MARIO CUEVAS |
| Drywall Nailing | 4/8/2022 | Approved | MARIO CUEVAS |
| Interior/Exterior Lathing | 4/8/2022 | Approved | MARIO CUEVAS |
| Final | 6/14/2022 | Corrections Issued | MARIO CUEVAS |
| Green Building Final | 6/14/2022 | Not Ready for Inspection | MARIO CUEVAS |
| SGSOV-Seismic Gas S/O Valve | 6/14/2022 | SGSOV Not Ready | MARIO CUEVAS |
| Smoke Detectors | 6/14/2022 | Corrections Issued | MARIO CUEVAS |
| Final | 6/22/2022 | Conditional Approval | MARIO CUEVAS |
| Green Building Final | 6/22/2022 | Approved | MARIO CUEVAS |
| SGSOV-Seismic Gas S/O Valve | 6/22/2022 | SGSOV Approved | MARIO CUEVAS |
| Smoke Detectors | 6/22/2022 | Approved | MARIO CUEVAS |