975 W 19TH ST 1-5 90731

Certificate Information: 975 W 19TH ST 1-5 90731

Application / Permit
21016-10000-24018
Plan Check / Job No.
B21LA16617
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CONVERT EXISTING LOBBY AND RECREATION ROOM TO ADU (1475 SF)
Permit Issued
Issued on 1/27/2022
Issuing Office
Current Status
CofO Issued on 11/9/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/3/2021 APPLICANT
Assigned to Plan Check Engineer 9/23/2021 JOE VO
Corrections Issued 9/26/2021 JOE VO
Quality Review Completed 10/12/2021 MICHAEL PEREZ
Applicant returned to address corrections 11/13/2021 JOE VO
Plan Check Approved 1/11/2022 JOE VO
Issued 1/27/2022 APPLICANT
CofO in Progress 11/7/2022 JOEY BUCHANAN
Permit Finaled 11/9/2022 DAVID TSAU
CofO Issued 11/9/2022 DAVID TSAU
Permit Finaled 11/9/2022 DAVID TSAU

Permit Application Clearance Information

Address approval Cleared 10/1/2021 JOSE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 10/22/2021 JOSE HERNANDEZ
Sewer availability Cleared 10/22/2021 JOSE HERNANDEZ
Grading Pre-Inspection Cleared 11/5/2021 VASIL MIHALEV
Hydrant and Access approval Cleared 12/10/2021 MATTHEW CRAIG
Tenant Habitability Plan Cleared 1/10/2022 MICHAEL SOTO

Contact Information

Architect Puskar,, Heidi M; Lic. No.: C28223 29431 N ENROSE AVENUE      RANCHO PALOS VERDES, CA 90275
Contractor M A F Construction Inc; Lic. No.: 540983-B 1000 N WESTERN AVENUE STE 201      SAN PEDRO, CA 90732

Inspector Information

MICHAEL PETRUSKO, (310) 732-4552 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/18/2022 Approved JOEY BUCHANAN
Interior/Exterior Lathing 5/12/2022 Partial Approval DAVID TSAU
Wood Frame 7/19/2022 Approved JOEY BUCHANAN
Insulation 7/25/2022 Approved JOEY BUCHANAN
Drywall Nailing 7/28/2022 Approved JOEY BUCHANAN
Interior/Exterior Lathing 8/5/2022 Approved DAVID TSAU
Final 11/2/2022 Not Ready for Inspection JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 11/2/2022 SGSOV Approved JOEY BUCHANAN
Smoke Detectors 11/2/2022 Approved JOEY BUCHANAN
Final 11/7/2022 OK to Issue CofO JOEY BUCHANAN