203 W WAYLAND ST 90042
Certificate Information: 203 W WAYLAND ST 90042
- Application / Permit
- 21016-10000-24013
- Plan Check / Job No.
- B21LA16615
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE INTO ADU.
- Permit Issued
- Issued on 12/14/2021
- Issuing Office
- Current Status
- CofO Issued on 7/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/6/2021 | JOE VO |
| Corrections Issued | 9/7/2021 | JOE VO |
| Plan Check Approved | 11/30/2021 | JOE VO |
| Issued | 12/14/2021 | APPLICANT |
| Refund in Progress | 9/30/2022 | TERENCE SHIA |
| Refund in Progress | 9/30/2022 | TERENCE SHIA |
| Refund Denied | 11/7/2022 | EMILY HU |
| Issued | 11/7/2022 | EMILY HU |
| Refund Denied | 11/18/2022 | EMILY HU |
| Issued | 11/18/2022 | EMILY HU |
| CofO in Progress | 6/12/2023 | JAVIER RAMOS SR |
| CofO in Progress | 6/12/2023 | JAVIER RAMOS SR |
| Permit Finaled | 7/10/2023 | DANIEL SANCHEZ |
| CofO Issued | 7/10/2023 | DANIEL SANCHEZ |
| Permit Finaled | 7/10/2023 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Address approval | Cleared | 9/13/2021 | WALLIE JONG |
| Sewer availability | Cleared | 9/13/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/21/2021 | WALLIE JONG |
| HPOZ | Cleared | 9/28/2021 | KATIE DEBIASE |
| Historic monument | Cleared | 9/28/2021 | KATIE DEBIASE |
| Miscellaneous | Cleared | 12/14/2021 | KURT CORRAL |
Contact Information
| Contractor | Levelworks Construct & Renovate Inc; Lic. No.: 1044710-B | 2600 W OLIVE AVE STE 5430 BURBANK, CA 91505 |
| Engineer | Dominguez,, Refugio; Lic. No.: NA50820 | , |
Inspector Information
| THOMAS WILLIS, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| JEFFREY CHRISTIAN, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| FERMIN RUBIO, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| JACOB SEGURA, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| CLAUDIO MORENO, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK RUDE, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/31/2022 | Corrections Issued | JAVIER RAMOS SR |
| Special/Order Compliance | 2/1/2022 | Corrections Issued | JAVIER RAMOS SR |
| Pre-Inspection | 3/21/2022 | Approved | JAVIER RAMOS SR |
| Excavation/Setback/Form/Re-Bar | 3/30/2022 | Approved | JAVIER RAMOS SR |
| Footing/Foundation/Slab | 3/30/2022 | Approved | JAVIER RAMOS SR |
| Underground Mechanical | 3/30/2022 | Partial Approval | JAVIER RAMOS SR |
| Gas Test | 4/26/2022 | Approved | JAVIER RAMOS SR |
| Sewer | 4/26/2022 | Approved | JAVIER RAMOS SR |
| Underground Mechanical | 4/26/2022 | Approved | JAVIER RAMOS SR |
| Footing/Foundation/Slab | 5/11/2022 | Approved | JAVIER RAMOS SR |
| ELECTRICAL-Rough | 5/24/2022 | Partial Approval | JAVIER RAMOS SR |
| PLUMBING-Rough | 5/24/2022 | Partial Approval | JAVIER RAMOS SR |
| BUILDING-Rough-Frame | 5/31/2022 | Approved | JAVIER RAMOS SR |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2022 | Approved | JAVIER RAMOS SR |
| Insulation | 6/9/2022 | Approved | JAVIER RAMOS SR |
| Interior/Exterior Lathing | 6/9/2022 | Partial Approval | JAVIER RAMOS SR |
| Shower Pan | 6/10/2022 | Not Ready for Inspection | JAVIER RAMOS SR |
| Drywall Nailing | 6/13/2022 | Approved | JAVIER RAMOS SR |
| ELECTRICAL-Final | 11/9/2022 | Approved | JAVIER RAMOS SR |
| Final | 11/9/2022 | Not Ready for Inspection | JAVIER RAMOS SR |
| Gas Test | 11/9/2022 | Approved | JAVIER RAMOS SR |
| HVAC-Final | 11/9/2022 | Corrections Issued | JAVIER RAMOS SR |
| HVAC-Rough | 11/9/2022 | Not Ready for Inspection | JAVIER RAMOS SR |
| Interior/Exterior Lathing | 11/9/2022 | Approved | JAVIER RAMOS SR |
| PLUMBING-Final | 11/9/2022 | Approved | JAVIER RAMOS SR |
| SGSOV-Seismic Gas S/O Valve | 11/9/2022 | SGSOV Approved | JAVIER RAMOS SR |
| Shower Pan | 11/9/2022 | Approved | JAVIER RAMOS SR |
| Smoke Detectors | 11/9/2022 | Approved | JAVIER RAMOS SR |
| Final | 1/9/2023 | OK to Issue CofO | JAVIER RAMOS SR |