624 W 38TH ST 90731

Certificate Information: 624 W 38TH ST 90731

Application / Permit
21016-10000-24007
Plan Check / Job No.
B21LA16611
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(7) Garage - Private
Work Description
ADDITION & REMODEL TO (E) GARAGE
Permit Issued
Issued on 5/3/2022
Issuing Office
Metro
Current Status
CofO Issued on 8/26/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/3/2021 APPLICANT
Assigned to Plan Check Engineer 9/23/2021 LAMAR DAVIS
Corrections Issued 9/28/2021 LAMAR DAVIS
Quality Review Completed 10/7/2021 WING SUEN
Applicant returned to address corrections 2/15/2022 LAMAR DAVIS
Building Plans Picked Up 2/15/2022 APPLICANT
Plan Check Approved 4/19/2022 LAMAR DAVIS
Issued 5/3/2022 APPLICANT
CofO in Progress 8/26/2024 AMANUEL BERHE
Permit Finaled 8/26/2024 JOEY BUCHANAN
CofO Issued 8/26/2024 JOEY BUCHANAN
Permit Finaled 8/26/2024 JOEY BUCHANAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/10/2022 ERIK BEASLEY
Roof/Waste drainage to street Cleared 1/10/2022 ERIK BEASLEY
Coastal Zone Cleared 1/20/2022 RUBEN VASQUEZ
Green Code Cleared 3/25/2022 NEGAR NEJAD
Grading Pre-Inspection Cleared 4/19/2022 JONATHAN HOM

Contact Information

Contractor Owner-Builder       ,
Engineer Alson,, Ken; Lic. No.: C41697 9744 MAPLE ST 201      BELLFLOWER, CA 90706

Inspector Information

MICHAEL PETRUSKO, (310) 732-4552 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/25/2022 Approved JOEY BUCHANAN
Footing/Foundation/Slab 5/25/2022 Approved JOEY BUCHANAN
Green Building Rough 6/27/2022 Approved JOEY BUCHANAN
Wood Frame 6/27/2022 Corrections Issued JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 7/15/2022 Not Ready for Inspection JOEY BUCHANAN
Wood Frame 7/15/2022 Not Ready for Inspection JOEY BUCHANAN
Wood Frame 9/16/2022 Approved JOEY BUCHANAN
Drywall Nailing 7/28/2023 Approved JOEY BUCHANAN
Final 7/28/2023 Conditional Approval JOEY BUCHANAN
Green Building Final 7/28/2023 Approved JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 7/28/2023 SGSOV Approved JOEY BUCHANAN
Smoke Detectors 7/28/2023 Approved JOEY BUCHANAN
Final 3/1/2024 Partial Approval AMANUEL BERHE
Final 8/26/2024 OK to Issue CofO AMANUEL BERHE