14743 W VENTURA BLVD 91403
Certificate Information: 14743 W VENTURA BLVD 91403
- Application / Permit
- 21016-10000-23800
- Plan Check / Job No.
- B21LA16520
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Medical Office
- Work Description
- CHANGE OF USE FROM RESTAURANT TO MEDICAL OFFICE. TENANT IMPROVEMENT WORK ON +/- 8200 SQ/FT OF THE TOTAL FLOOR AREA. NEW WALL, POWER, CEILING, LIGHTING AND FINISHES.
- Permit Issued
- Issued on 3/31/2022
- Issuing Office
- Current Status
- CofO Issued on 12/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/14/2021 | JOE VO |
| Corrections Issued | 11/3/2021 | JOE VO |
| Quality Review Completed | 11/16/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 2/28/2022 | JOE VO |
| Disabled Access Plans Picked Up | 3/2/2022 | APPLICANT |
| Plan Check Approved | 3/23/2022 | JOE VO |
| Issued | 3/31/2022 | APPLICANT |
| Building Plans Picked Up | 4/1/2022 | APPLICANT |
| CofO in Progress | 11/15/2022 | ANDREW DORSO |
| CofO Issued | 12/1/2022 | JEFFREY DURAN |
| Permit Finaled | 12/1/2022 | JEFFREY DURAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/15/2021 | CARLOS AGUILERA |
| ZA Case | Cleared | 12/17/2021 | DANIEL CORONADO |
| ZA Case | Cleared | 12/17/2021 | DANIEL CORONADO |
| Specific Plan | Cleared | 1/21/2022 | CORREY KITCHENS |
| Sewer availability | Cleared | 2/14/2022 | CARLOS AGUILERA |
| DAS Clearance | Cleared | 3/7/2022 | JOE VO |
| Green Code | Cleared | 3/14/2022 | JOE VO |
Contact Information
| Architect | Algaze,, Nelson; Lic. No.: C21090 | 1524 1ST STREET MANHATTAN BEACH, CA 90266 |
| Contractor | Schneider Tim Construction Inc; Lic. No.: 724075-B | 3835 E THOUSAND OAKS BLVD #232 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/26/2022 | Partial Inspection | DANIEL VARNUM |
| Footing/Foundation/Slab | 5/10/2022 | Approved | DANIEL VARNUM |
| Light Gage Steel Frame | 7/15/2022 | Partial Approval | DANIEL VARNUM |
| Drywall Nailing | 8/1/2022 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 8/10/2022 | Approved | DANIEL VARNUM |
| T-Bar Ceiling | 9/16/2022 | Not Ready for Inspection | DANIEL VARNUM |
| T-Bar Ceiling | 9/20/2022 | Conditional Approval | DANIEL VARNUM |
| Pre-Inspection | 10/27/2022 | Partial Inspection | ANDREW DORSO |
| Final | 11/2/2022 | Not Ready for Inspection | ANDREW DORSO |
| Green Building Final | 11/2/2022 | Approved | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 11/2/2022 | SGSOV Approved | ANDREW DORSO |
| Smoke Detectors | 11/2/2022 | Not Ready for Inspection | ANDREW DORSO |
| Final | 11/8/2022 | OK to Issue CofO | ANDREW DORSO |
| Smoke Detectors | 11/8/2022 | Approved | ANDREW DORSO |