1425 W 55TH ST 90062
Certificate Information: 1425 W 55TH ST 90062
- Application / Permit
- 21016-10000-23640
- Plan Check / Job No.
- B21LA16477
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ONE STORY ADDITION ( 12'-0" W X 9'-0" L ) TO REAR OF EXISTING SINGLE FAMILY DWELLING TO ENLARGE PRIMARY BEDROOM AND CREATE EN-SUITE BATHROOM . AND ADD ( 7'-0" W X 9'-0" L ) COVERED DECK AT REAR. AND REFRAME THE ROOF AT THE REAR . WORK PER WOOD FRAME PRESCRIPTIVE PROVISIONS.
- Permit Issued
- Issued on 3/8/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/3/2021 | TSE MING HUANG |
| Corrections Issued | 9/4/2021 | TSE MING HUANG |
| Building Plans Picked Up | 12/2/2021 | APPLICANT |
| Quality Review Completed | 1/11/2022 | STANLEY RAAP |
| Plan Check Approved | 5/10/2022 | JESSE JIMENEZ |
| No Progress | 12/6/2022 | YAQUB MIRZA |
| Plan Check Approved | 3/2/2023 | GEORGE ALVAREZ |
| Issued | 3/8/2023 | APPLICANT |
| CofO in Progress | 10/24/2023 | BRENDAN MORELLI |
| Permit Finaled | 10/29/2023 | DEROLD HAUFF |
| CofO Issued | 10/29/2023 | DEROLD HAUFF |
| Permit Finaled | 10/29/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/19/2022 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 4/19/2022 | JEANIE LAM |
| Sewer availability | Cleared | 4/19/2022 | JEANIE LAM |
| Community Plan Implem. Overlay | Cleared | 5/2/2022 | RAFAEL FONTES |
| Miscellaneous | Cleared | 5/2/2022 | RAFAEL FONTES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/25/2023 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 5/8/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 5/16/2023 | Corrections Issued | SABAS ALONSO |
| Insulation | 5/17/2023 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 5/17/2023 | Partial Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 5/24/2023 | Not Ready for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2023 | Partial Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 6/6/2023 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 6/6/2023 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 6/12/2023 | Approved | SABAS ALONSO |
| Green Building Rough | 6/12/2023 | Approved | SABAS ALONSO |
| HVAC-Rough | 6/12/2023 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 6/12/2023 | Partial Approval | SABAS ALONSO |
| HVAC-Rough | 6/15/2023 | Corrections Issued | SABAS ALONSO |
| Insulation | 6/15/2023 | Approved | SABAS ALONSO |
| Drywall Nailing | 6/21/2023 | Approved | ALEJANDRO DE ARTOLA |
| Shower Pan | 6/21/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Shower Pan | 7/7/2023 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 7/17/2023 | Approved | CHARLES BOGHOSKHAN |
| Final | 9/19/2023 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 9/19/2023 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 9/19/2023 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 9/19/2023 | Corrections Issued | SABAS ALONSO |
| Final | 10/23/2023 | OK to Issue CofO | BRENDAN MORELLI |
| Smoke Detectors | 10/23/2023 | Approved | BRENDAN MORELLI |