4913 N KESTER AVE 91403
Certificate Information: 4913 N KESTER AVE 91403
- Application / Permit
- 21016-10000-23311
- Plan Check / Job No.
- B21LA16365
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF TWO CAR GARAGE INTO ADU PER 65852.2 (e) (1) (c).
- Permit Issued
- Issued on 6/17/2022
- Issuing Office
- Current Status
- CofO Issued on 12/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/3/2021 | TSE MING HUANG |
| Corrections Issued | 9/4/2021 | TSE MING HUANG |
| Building Plans Picked Up | 10/5/2021 | APPLICANT |
| Plan Check Approved | 10/21/2021 | JOSEPH RAFOLS |
| Issued | 6/17/2022 | APPLICANT |
| CofO in Progress | 12/14/2022 | JEFFREY FULTON |
| Permit Finaled | 12/14/2022 | JEFFREY DURAN |
| CofO Issued | 12/14/2022 | JEFFREY DURAN |
| Permit Finaled | 12/14/2022 | JEFFREY DURAN |
Permit Application Clearance Information
| Address approval | Cleared | 9/14/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 9/14/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 9/15/2021 | CARLOS AGUILERA |
| "Q" conditions | Cleared | 9/16/2021 | JOE LUCKEY |
| Tenant Habitability Plan | Cleared | 10/21/2021 | JORGE ALCANTAR |
Contact Information
| Contractor | Rent Ready Construction Inc; Lic. No.: 1065376-B | 631 N SIERRA BONITA AVE LOS ANGELES, CA 90036 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/25/2022 | Conditional Approval | DANIEL VARNUM |
| Footing/Foundation/Slab | 8/25/2022 | Approved | DANIEL VARNUM |
| Deputy Drilled-In Anchors | 9/7/2022 | Conditional Approval | DANIEL VARNUM |
| Interior/Exterior Lathing | 9/26/2022 | Conditional Approval | CAMERON CHABAN |
| Wood Frame | 9/26/2022 | Approved | CAMERON CHABAN |
| Insulation | 9/30/2022 | Approved | KENNETH ROBERTS |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2022 | Partial Approval | DANIEL VARNUM |
| Drywall Nailing | 10/5/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Drywall Nailing | 10/7/2022 | Approved | DANIEL VARNUM |
| Interior/Exterior Lathing | 10/11/2022 | Approved | DANIEL VARNUM |
| Final | 12/6/2022 | OK to Issue CofO | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 12/6/2022 | SGSOV Approved | JEFFREY FULTON |
| Smoke Detectors | 12/6/2022 | Approved | JEFFREY FULTON |