2651 S STONER AVE 90064
Certificate Information: 2651 S STONER AVE 90064
- Application / Permit
- 21016-10000-23285
- Plan Check / Job No.
- B21LA16353
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 12/2/2021
- Issuing Office
- Current Status
- CofO Issued on 12/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/31/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2021 | SELLA BENYAMIN |
| Corrections Issued | 9/2/2021 | DANIEL YIP |
| Plan Check Approved | 11/20/2021 | SELLA BENYAMIN |
| Issued | 12/2/2021 | APPLICANT |
| CofO in Progress | 12/22/2022 | DANIEL ORRANTE |
| Permit Finaled | 12/22/2022 | DANIEL ORRANTE |
| CofO Issued | 12/22/2022 | DANIEL ORRANTE |
| Permit Finaled | 12/22/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 9/9/2021 | DINAH GARIN |
| Sewer availability | Cleared | 9/9/2021 | DINAH GARIN |
| Specific Plan | Cleared | 9/30/2021 | PETE EYRE |
| Eng Process Fee Ord 176,300 | Cleared | 10/5/2021 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 11/16/2021 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/20/2022 | Conditional Approval | JOHNNY MIRANDA |
| Green Building Rough | 5/5/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Wood Frame | 5/5/2022 | Corrections Issued | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2022 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 6/3/2022 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 6/3/2022 | Approved | JOHNNY MIRANDA |
| Wood Frame | 6/3/2022 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 9/28/2022 | Approved | ANDREW NAVE |
| Final | 9/28/2022 | Corrections Issued | ANDREW NAVE |
| Green Building Final | 9/28/2022 | Corrections Issued | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 9/28/2022 | SGSOV Not Ready | ANDREW NAVE |
| Smoke Detectors | 9/28/2022 | Corrections Issued | ANDREW NAVE |
| Final | 10/21/2022 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Final | 10/21/2022 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 10/21/2022 | SGSOV Approved | JOHNNY MIRANDA |
| Smoke Detectors | 10/21/2022 | Approved | JOHNNY MIRANDA |
| Final | 11/7/2022 | Conditional Approval | KENNETH NAGLE |
| Final | 11/18/2022 | Conditional Approval | JOHNNY MIRANDA |