5563 W ADAMS BLVD 90016
Certificate Information: 5563 W ADAMS BLVD 90016
- Application / Permit
- 21016-10000-23181
- Plan Check / Job No.
- B21LA16297
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- ePLAN. CHANGE OF USE FROM RETAIL TO OFFICE. INTERIOR TENANT IMPROVEMENT.
- Permit Issued
- Issued on 11/11/2021
- Issuing Office
- Current Status
- Issued on 11/11/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/1/2021 | KEVIN MORALES |
| Corrections Issued | 9/2/2021 | KEVIN MORALES |
| Applicant returned to address corrections | 9/13/2021 | KEVIN MORALES |
| Applicant returned to address corrections | 9/17/2021 | KEVIN MORALES |
| Plan Check Approved | 11/4/2021 | KEVIN MORALES |
| Issued | 11/11/2021 | APPLICANT |
Permit Application Clearance Information
| Food establishment approval | Cleared | 10/1/2021 | LACDHS APPROVED |
| ZA Case | Cleared | 10/5/2021 | DANIEL CORONADO |
| Historic Resource Verification | Cleared | 10/8/2021 | MICAELA TORRES-GIL |
| Redevelopment Project Area | Cleared | 10/13/2021 | DAVID URITA |
| Eng Process Fee Ord 176,300 | Cleared | 10/18/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 10/18/2021 | CECILIO NAVARRO |
| Community Plan Implem. Overlay | Cleared | 11/1/2021 | KYLE WINSTON |
Contact Information
| Architect | Algaze,, Nelson; Lic. No.: NA21090 | , |
| Contractor | Prime Construction & Development Inc.; Lic. No.: 818299-B | 895 N FAIR OAKS AVENUE PASADENA, CA 91103 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 6/8/2022 | Corrections Issued | KATY RAMIREZ |
| Insulation | 6/16/2022 | Partial Approval | KATY RAMIREZ |
| Drywall Nailing | 6/27/2022 | Partial Approval | GREGORY POMISH |
| T-Bar Ceiling | 7/15/2022 | Approved | EDWIN GREGORYONA |
| Final | 9/15/2022 | Partial Inspection | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 9/15/2022 | SGSOV Approved | KATY RAMIREZ |
| Smoke Detectors | 9/15/2022 | Approved | KATY RAMIREZ |