6006 E LA PRADA 90042
Certificate Information: 6006 E LA PRADA 90042
- Application / Permit
- 21016-10000-23087
- Plan Check / Job No.
- B21LA16209
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and repair to (E) attached garage with roof top deck. Remodel (E) single family.
- Permit Issued
- Issued on 12/22/2021
- Issuing Office
- Current Status
- CofO Issued on 9/8/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/31/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2021 | ZAW HAN |
| Corrections Issued | 9/7/2021 | ZAW HAN |
| Applicant returned to address corrections | 10/18/2021 | LUKE GONZALES |
| Applicant returned to address corrections | 11/5/2021 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 11/19/2021 | ZAW HAN |
| Plan Check Approved | 12/14/2021 | SHANGQIN XIE |
| Issued | 12/22/2021 | APPLICANT |
| Building Plans Picked Up | 12/29/2021 | APPLICANT |
| CofO in Progress | 9/2/2022 | CRAIG VAUGHAN |
| Permit Finaled | 9/8/2022 | DEROLD HAUFF |
| CofO Issued | 9/8/2022 | DEROLD HAUFF |
| Permit Finaled | 9/8/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/20/2021 | VASIL MIHALEV |
| Eng Process Fee Ord 176,300 | Cleared | 9/28/2021 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 12/3/2021 | JEANETTE VONG |
| Sewer availability | Cleared | 12/3/2021 | JEANETTE VONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Galbreath,, Sean Martin; Lic. No.: S5653 | 600 SOUTH LAKE AVE STE 308 PASADENA, CA 91106 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 1/3/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 1/12/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Pre-Inspection | 1/14/2022 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 2/10/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 2/10/2022 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Rough | 2/10/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 2/10/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 2/17/2022 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 2/17/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 2/25/2022 | Corrections Issued | SCOTT FINNILA |
| Green Building Rough | 2/25/2022 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Rough | 2/25/2022 | Approved | SCOTT FINNILA |
| BUILDING-Rough-Frame | 3/3/2022 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 3/3/2022 | Approved | CRAIG VAUGHAN |
| Insulation | 3/7/2022 | Approved | CHARLES BOGHOSKHAN |
| Drywall Nailing | 3/15/2022 | Approved | CHARLES BOGHOSKHAN |
| Interior/Exterior Lathing | 4/12/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Shower Pan | 4/12/2022 | Approved | ALIZAH MAYAGOITIA |
| Final | 8/19/2022 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 8/19/2022 | Approved | CRAIG VAUGHAN |
| Green Building Final | 8/19/2022 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 8/19/2022 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 8/19/2022 | Approved | CRAIG VAUGHAN |
| Final | 8/29/2022 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Final | 9/1/2022 | Approved | CRAIG VAUGHAN |
| Final | 9/1/2022 | OK to Issue CofO | CRAIG VAUGHAN |
| HVAC-Final | 9/1/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 9/1/2022 | Approved | CRAIG VAUGHAN |