10510 W KURT ST 91342
Certificate Information: 10510 W KURT ST 91342
- Application / Permit
- 21016-10000-22978
- Plan Check / Job No.
- B21LA16145
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT ATTACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER STATE LAW.
- Permit Issued
- Issued on 2/3/2022
- Issuing Office
- Current Status
- CofO Issued on 9/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2021 | LAWRENCE QUIRANTE |
| Corrections Issued | 9/4/2021 | LAWRENCE QUIRANTE |
| Plan Check Approved | 10/6/2021 | JOSEPH RAFOLS |
| Building Plans Picked Up | 10/12/2021 | APPLICANT |
| No Progress | 10/29/2021 | JOSEPH RAFOLS |
| Issued | 2/3/2022 | APPLICANT |
| CofO in Progress | 9/1/2022 | MATTHEW NELSON |
| Permit Finaled | 9/15/2022 | MICHAEL SMITH |
| CofO Issued | 9/15/2022 | MICHAEL SMITH |
| Permit Finaled | 9/15/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 9/10/2021 | DAGOVERTO GUERRERO |
| Grading Pre-Inspection | Cleared | 9/13/2021 | PATRICK MISCHLICH |
| Eng Process Fee Ord 176,300 | Cleared | 9/14/2021 | DAGOVERTO GUERRERO |
| Specific Plan | Cleared | 9/20/2021 | PEGGY MALONE-BROWN |
| Private sewage disp. approval | Cleared | 2/2/2022 | PATRICK MISCHLICH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 | 2160 PARNELL WY ALTADENA, CA 91001 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/10/2022 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 3/16/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 3/22/2022 | Partial Approval | MATTHEW NELSON |
| Pre-Inspection | 3/22/2022 | Partial Inspection | MATTHEW NELSON |
| Sewer | 4/21/2022 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 5/5/2022 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 5/5/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 5/5/2022 | Approved | MATTHEW NELSON |
| Insulation | 5/12/2022 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 5/12/2022 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2022 | Approved | MATTHEW NELSON |
| Drywall Nailing | 5/18/2022 | Approved | MATTHEW NELSON |
| Deputy Wood Construction | 5/19/2022 | Partial Approval | MATTHEW NELSON |
| Shower Pan | 5/24/2022 | Approved | MATTHEW NELSON |
| Final | 8/4/2022 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 8/4/2022 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 8/4/2022 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 9/1/2022 | Approved | MATTHEW NELSON |
| Final | 9/1/2022 | OK to Issue CofO | MATTHEW NELSON |
| HVAC-Final | 9/1/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 9/1/2022 | Approved | MATTHEW NELSON |