7253 W MELROSE AVE 90046
Certificate Information: 7253 W MELROSE AVE 90046
- Application / Permit
- 21016-10000-22682
- Plan Check / Job No.
- B21LA16014
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (11) Homeless Shelter
- Work Description
- EMERGENCY HOMELESS SHELTER PER LAMC SECTION 12.80 AND LAFD DIRECTIVE 45, SECTION II. NFPA 13 FIRE SPRINKLERS REQUIRED.
- Permit Issued
- Issued on 4/26/2023
- Issuing Office
- Current Status
- CofO Issued on 1/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/16/2021 | KEVIN MORALES |
| Corrections Issued | 9/24/2021 | KEVIN MORALES |
| Quality Review Completed | 9/27/2021 | EUGENE BARBEAU |
| Applicant returned to address corrections | 2/2/2022 | KEVIN MORALES |
| Plan Check Approved | 2/18/2022 | KEVIN MORALES |
| Issued | 4/26/2023 | APPLICANT |
| Building Plans Picked Up | 5/1/2023 | APPLICANT |
| CofO in Progress | 1/10/2025 | MARTIN TAVITIAN |
| CofO Issued | 1/10/2025 | ERNESTO CORRAL |
| Permit Finaled | 1/10/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Fire Marshal Fire Life Safety | Cleared | 12/22/2021 | MENOA AGHAJANI |
| Eng Process Fee Ord 176,300 | Cleared | 1/3/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 1/3/2022 | STEVE MELGAR |
| Green Code | Cleared | 1/12/2022 | EUGENE BARBEAU |
| Hydrant and Access approval | Cleared | 1/24/2022 | JOHN CONNEALLY |
| DAS Clearance | Cleared | 1/25/2022 | EUGENE BARBEAU |
Contact Information
| Contractor | Casa Mia Construction Inc; Lic. No.: 1005133-B | 17412 VENTURA BLVD SUITE 28 ENCINO, CA 91316 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 7/19/2023 | Partial Inspection | JEROME BLACKWOOD |
| METHANE-Rough | 7/19/2023 | Approved | JEROME BLACKWOOD |
| Wood Frame | 7/19/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Green Building Rough | 7/28/2023 | Partial Inspection | GREGORY POMISH |
| Wood Frame | 7/28/2023 | Partial Inspection | GREGORY POMISH |
| Green Building Rough | 1/29/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Wood Frame | 1/29/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Green Building Rough | 2/1/2024 | Partial Inspection | JACOB MYERS |
| Wood Frame | 2/1/2024 | Partial Approval | JACOB MYERS |
| Green Building Rough | 2/21/2024 | Approved | ALFREDO LOPEZ |
| Insulation | 2/21/2024 | Partial Approval | ALFREDO LOPEZ |
| Wood Frame | 2/21/2024 | Partial Approval | ALFREDO LOPEZ |
| Pre-Inspection | 3/6/2024 | Partial Inspection | JACOB MYERS |
| Special/Order Compliance | 3/6/2024 | Corrections Issued | MARTIN TAVITIAN |
| Drywall Nailing | 3/29/2024 | Partial Approval | MARTIN TAVITIAN |
| Interior/Exterior Lathing | 3/29/2024 | Not Ready for Inspection | MARTIN TAVITIAN |
| Interior/Exterior Lathing | 4/5/2024 | Partial Approval | JACOB MYERS |
| Interior/Exterior Lathing | 5/7/2024 | Partial Approval | JACOB MYERS |
| Special/Order Compliance | 5/14/2024 | Corrections Issued | JACOB MYERS |
| Interior/Exterior Lathing | 7/1/2024 | Partial Approval | MARTIN TAVITIAN |
| Pre-Inspection | 7/8/2024 | Partial Approval | MARTIN TAVITIAN |
| Final | 11/22/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Final | 11/22/2024 | Not Ready for Inspection | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 11/22/2024 | SGSOV Not Ready | RAFAEL CORTES |
| Smoke Detectors | 11/22/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 11/22/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 12/18/2024 | Partial Inspection | TIMOTHY POWELL |
| Green Building Final | 12/18/2024 | Approved | TIMOTHY POWELL |
| SGSOV-Seismic Gas S/O Valve | 12/18/2024 | SGSOV Approved | TIMOTHY POWELL |
| Smoke Detectors | 12/18/2024 | Approved | TIMOTHY POWELL |
| Wood Frame | 12/18/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| Final | 12/23/2024 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Wood Frame | 12/23/2024 | Approved | RAFAEL ESPINOZA |
| Final | 12/27/2024 | Corrections Issued | RAFAEL ESPINOZA |
| Final | 1/10/2025 | OK to Issue CofO | MARTIN TAVITIAN |