500 E TEMPLE ST 90012

Certificate Information: 500 E TEMPLE ST 90012

Application / Permit
21016-10000-22602
Plan Check / Job No.
B21LA15964
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
EXTERIOR RENOVATION; REPLACEMENT OF EXISTING STONE TILE VENEER WITH NEW PLASTER FINISH ALONG THE SECOND FLOOR AT BOTH THE EXISTING FIRE STATION AND EMERGENCY OPERATIONS CENTER BUILDINGS. WORK TO INCLUDE DEMOLITION OF THE EXISTING STONE TILE VENEER. THE SCOPE OF WORK IS LIMITED TO THE EXTERIOR ALONG BOTH BUILDINGS. 2 OF 2
Permit Issued
Issued on 3/30/2022
Issuing Office
Metro
Current Status
Permit Finaled on 2/15/2024

Permit Application Status History

Submitted 9/2/2021 APPLICANT
Assigned to Plan Check Engineer 10/1/2021 TSE MING HUANG
Corrections Issued 10/3/2021 TSE MING HUANG
Quality Review Completed 10/5/2021 STANLEY RAAP
Green Plans Picked Up 12/23/2021 APPLICANT
Plan Check Approved 2/15/2022 STANLEY RAAP
Disabled Access Plans Picked Up 2/17/2022 APPLICANT
Issued 3/30/2022 APPLICANT
Building Plans Picked Up 4/4/2022 APPLICANT
Permit Finaled 2/15/2024 RONALD JIMENEZ

Permit Application Clearance Information

DAS Clearance Cleared 11/30/2021 TSE MING HUANG
"D" conditions Cleared 12/8/2021 MAXFIELD VERMY
"Q" conditions Cleared 12/8/2021 MAXFIELD VERMY
City owned building/parcel Cleared 12/8/2021 TSE MING HUANG
ZI Cleared 12/8/2021 MAXFIELD VERMY
Green Code Cleared 12/21/2021 AARON COSTA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/3/2022 Corrections Issued MARK FERRARI
Light Gage Steel Frame 12/1/2022 Approved RAFAEL CORTES
Drywall Nailing 12/12/2022 Corrections Issued MARK FERRARI
Drywall Nailing 1/23/2023 Partial Approval RAFAEL CORTES
Drywall Nailing 1/25/2023 Approved RAMAZANALI ALMASI
Interior/Exterior Lathing 2/8/2023 Partial Approval JULIAN CAPUCETTI
Interior/Exterior Lathing 3/1/2023 Partial Approval JULIAN CAPUCETTI
Final 5/25/2023 Partial Inspection JULIAN CAPUCETTI
Green Building Final 5/25/2023 Partial Approval JULIAN CAPUCETTI
SGSOV-Seismic Gas S/O Valve 5/25/2023 SGSOV Gas Company JULIAN CAPUCETTI
Smoke Detectors 5/25/2023 Approved JULIAN CAPUCETTI
Final 2/15/2024 Permit Finaled RONALD JIMENEZ
Green Building Final 2/15/2024 Approved RONALD JIMENEZ