1722-1722 1/2 S BUTLER AVE 90025

Certificate Information: 1722-1722 1/2 S BUTLER AVE 90025

Application / Permit
21016-10000-22576
Plan Check / Job No.
B21LA15962
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
ePlan CHANGE 1ST FLOOR 2 COVERED PARKING GARAGES TO 2 ACCESSORY DWELLING UNITS GCS 65852.2 & 65852.22
Permit Issued
Issued on 11/18/2021
Issuing Office
Current Status
CofO Issued on 9/20/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/25/2021 APPLICANT
Assigned to Plan Check Engineer 8/27/2021 HERNAN ARREOLA
Corrections Issued 8/29/2021 HERNAN ARREOLA
Applicant returned to address corrections 9/20/2021 HERNAN ARREOLA
Plan Check Approved 11/11/2021 HERNAN ARREOLA
Issued 11/18/2021 APPLICANT
CofO in Progress 9/11/2024 CASIMIR BRITTON
Permit Finaled 9/20/2024 DAVID TSAU
CofO Issued 9/20/2024 DAVID TSAU
Permit Finaled 9/20/2024 DAVID TSAU

Permit Application Clearance Information

Address approval Cleared 9/7/2021 WALLIE JONG
Sewer availability Cleared 9/7/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 9/8/2021 WALLIE JONG
"Q" conditions Cleared 9/20/2021 KENTON TRINH
Specific Plan Cleared 10/6/2021 VALERIA CEJA
Tenant Habitability Plan Cleared 10/21/2021 RICHARD BRINSON

Contact Information

Contractor Retrofit 1; Lic. No.: 1003868-B 19326 VENTURA BLVD STE 200      TARZANA, CA 91356
Engineer Ni,, Zhang Yuan; Lic. No.: NA68149       ,

Inspector Information

CASIMIR BRITTON, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI
SHAVONNE ESPINOZA, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/26/2022 Approved JOHN DODGE
Pre-Inspection 4/28/2022 Corrections Issued JOHN DODGE
Footing/Foundation/Slab 7/11/2022 Approved GRANT WOODS
Interior/Exterior Lathing 10/25/2022 Partial Approval SORIN CIRSTOIU
Drywall Nailing 8/4/2023 Partial Inspection SORIN CIRSTOIU
Deputy Wood Construction 8/18/2023 Conditional Approval SORIN CIRSTOIU
Drywall Nailing 8/21/2023 Partial Approval SORIN CIRSTOIU
Drywall Nailing 8/25/2023 Approved SORIN CIRSTOIU
Interior/Exterior Lathing 8/30/2023 No Access for Inspection PAUL DAVIDSON
Footing/Foundation/Slab 4/26/2024 Not Ready for Inspection CASIMIR BRITTON
Final 8/14/2024 Not Ready for Inspection CASIMIR BRITTON
SGSOV-Seismic Gas S/O Valve 8/14/2024 SGSOV Not Ready CASIMIR BRITTON
Smoke Detectors 8/14/2024 Not Ready for Inspection CASIMIR BRITTON
Wood Frame 8/14/2024 Not Ready for Inspection CASIMIR BRITTON
Final 8/19/2024 Corrections Issued CASIMIR BRITTON
SGSOV-Seismic Gas S/O Valve 8/19/2024 SGSOV Not Ready CASIMIR BRITTON
Smoke Detectors 8/19/2024 Not Ready for Inspection CASIMIR BRITTON
Wood Frame 8/19/2024 Not Ready for Inspection CASIMIR BRITTON
Final 9/5/2024 Not Ready for Inspection CASIMIR BRITTON
SGSOV-Seismic Gas S/O Valve 9/5/2024 SGSOV Approved CASIMIR BRITTON
Smoke Detectors 9/5/2024 Approved CASIMIR BRITTON
Wood Frame 9/5/2024 Approved CASIMIR BRITTON
Final 9/11/2024 OK to Issue CofO CASIMIR BRITTON