129 E CLUB HOUSE AVE 90291

Certificate Information: 129 E CLUB HOUSE AVE 90291

Application / Permit
21016-10000-22517
Plan Check / Job No.
B21LA15926
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REPAIR FIRE DAMAGE TO (E) 1-STORY SINGLE FAMILY DWELLING. INTERIOR REMODEL, REMOVE AND REPAIR ROOF FRAMING, PORTION OF THE EXTERIOR WALL, WOOD DECK AND WINDOW.
Permit Issued
Issued on 2/7/2022
Issuing Office
Current Status
Permit Finaled on 4/12/2023

Permit Application Status History

Submitted 8/25/2021 APPLICANT
Assigned to Plan Check Engineer 9/16/2021 DANIEL YIP
Corrections Issued 9/21/2021 DANIEL YIP
Quality Review Completed 9/29/2021 ALLEN MANALANSAN
Building Plans Picked Up 9/30/2021 APPLICANT
Applicant returned to address corrections 12/17/2021 DANIEL YIP
Plan Check Approved 1/6/2022 DANIEL YIP
Issued 2/7/2022 APPLICANT
Permit Finaled 4/11/2023 KENNETH NAGLE

Permit Application Clearance Information

Historic monument Cleared 10/13/2021 LAMBERT GIESSINGER
Grading Pre-Inspection Cleared 10/15/2021 JONATHAN HOM
Tenant Habitability Plan Cleared 10/20/2021 MICHAEL SOTO
Specific Plan Cleared 11/1/2021 IRA BROWN
Eng Process Fee Ord 176,300 Cleared 11/18/2021 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 11/18/2021 HISASHI KOBAYAKAWA
Specific Plan Cleared 12/2/2021 PETE EYRE
Miscellaneous Cleared 12/3/2021 HISASHI KOBAYAKAWA

Contact Information

Contractor Ikon Builders Inc; Lic. No.: 966760-B 32158 CAMINO CAPISTRANO A 336      SAN JUAN CAPISTRANO, CA 92675
Engineer Hansen,, Hans Christian; Lic. No.: C80546 12831 MALENA DR      SANTA ANA, CA 92705
Engineer Zhao,, Xiaoming; Lic. No.: C70068 13402 PARK DR      CERRITOS, CA 90703

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/23/2022 Corrections Issued DAVID FEILER
Deputy Drilled-In Anchors 7/1/2022 Conditional Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 7/7/2022 Approved DAVID FEILER
BUILDING-Rough-Frame 7/28/2022 Not Ready for Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 7/28/2022 Partial Approval DAVID FEILER
METHANE-Rough 7/28/2022 Approved DAVID FEILER
HVAC-Rough 9/7/2022 Partial Approval DAVID FEILER
Rough-Elec/Plmb/HVAC 9/7/2022 Corrections Issued DAVID FEILER
ELECTRICAL-Rough 9/28/2022 Approved DAVID FEILER
HVAC-Rough 9/28/2022 Partial Approval DAVID FEILER
PLUMBING-Rough 9/28/2022 Approved DAVID FEILER
Wood Frame 9/28/2022 Partial Approval DAVID FEILER
Interior/Exterior Lathing 9/29/2022 Corrections Issued DAVID FEILER
BUILDING-Rough-Frame 10/5/2022 Conditional Approval DAVID FEILER
Insulation 10/5/2022 Approved DAVID FEILER
Interior/Exterior Lathing 10/7/2022 Partial Approval DAVID FEILER
Drywall Nailing 10/31/2022 Not Ready for Inspection DAVID FEILER
Interior/Exterior Lathing 10/31/2022 Corrections Issued DAVID FEILER
BUILDING-Rough-Frame 11/10/2022 Approved DAVID FEILER
Drywall Nailing 11/10/2022 Corrections Issued DAVID FEILER
Drywall Nailing 12/1/2022 Approved DAVID FEILER
Interior/Exterior Lathing 12/1/2022 Not Ready for Inspection DAVID FEILER
Interior/Exterior Lathing 1/10/2023 Partial Approval CLAYTON GRAHAM
HVAC-Final 2/28/2023 Corrections Issued EVAN COOPER
Service/Power Release 2/28/2023 Approved EVAN COOPER
Service/Power Release 3/14/2023 Approved EVAN COOPER
ELECTRICAL-Final 4/11/2023 Approved KENNETH NAGLE
Final 4/11/2023 Permit Finaled KENNETH NAGLE
HVAC-Final 4/11/2023 Approved KENNETH NAGLE
PLUMBING-Final 4/11/2023 Approved KENNETH NAGLE
SGSOV-Seismic Gas S/O Valve 4/11/2023 SGSOV Approved KENNETH NAGLE
Smoke Detectors 4/11/2023 Approved KENNETH NAGLE