3612 S KEYSTONE AVE 90034

Certificate Information: 3612 S KEYSTONE AVE 90034

Application / Permit
21016-10000-22504
Plan Check / Job No.
B21LA15914
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
REPLACE BALCONY WALL WITH STEEL GUARD SYSTEM AND REPLACE BALCONY FLOOR FRAMING. NEW GRAVITY COLUMNS AND PAD FOOTINGS
Permit Issued
Issued on 2/9/2022
Issuing Office
Current Status
Permit Finaled on 4/20/2023

Permit Application Status History

Submitted 8/30/2021 APPLICANT
Assigned to Plan Check Engineer 9/2/2021 LAWRENCE QUIRANTE
Corrections Issued 9/4/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 9/27/2021 GEORGE ALVAREZ
Plan Check Approved 1/24/2022 SINA KHOSRAVI
Building Plans Picked Up 1/28/2022 APPLICANT
Issued 2/9/2022 APPLICANT
Permit Finaled 4/13/2023 FARHAD DADBIN

Permit Application Clearance Information

Specific Plan Cleared 9/27/2021 DYLAN SITTIG
Grading Pre-Inspection Cleared 10/8/2021 PATRICK MISCHLICH
Tenant Habitability Plan Cleared 11/10/2021 RICHARD BRINSON

Contact Information

Contractor Procon Builders Inc; Lic. No.: 977214-A 9526 TOPANGA CANYON BLVD      CHATSWORTH, CA 91311
Engineer Talebian,, Sasan; Lic. No.: C44216 12063A JEFFERSON BLVD      CULVER CITY, CA 90230

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/4/2022 Approved NICK LAROCCA
Wood Frame 12/27/2022 Partial Approval GRANT WOODS
Interior/Exterior Lathing 1/30/2023 Not Ready for Inspection FARHAD DADBIN
Interior/Exterior Lathing 2/10/2023 Approved FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 3/29/2023 SGSOV Not Ready FARHAD DADBIN
Final 4/13/2023 Permit Finaled FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 4/13/2023 SGSOV Approved FARHAD DADBIN
Smoke Detectors 4/13/2023 Approved FARHAD DADBIN