9800 W PICO BLVD 90035

Certificate Information: 9800 W PICO BLVD 90035

Application / Permit
21016-10000-22049
Plan Check / Job No.
B21LA15765
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(18) Day Care Facility adults
Work Description
CHANGE OF USE FROM BANK/OFFICE TO ADULT CARE FACILITY. Structural support for new HVAC equipment.
Permit Issued
Issued on 4/7/2022
Issuing Office
Current Status
CofO Issued on 6/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/27/2021 APPLICANT
Assigned to Plan Check Engineer 9/16/2021 JOE VO
Corrections Issued 9/22/2021 JOE VO
Quality Review Completed 10/1/2021 LARRY LEE
Applicant returned to address corrections 12/13/2021 JOE VO
Plan Check Approved 4/5/2022 JOE VO
Issued 4/7/2022 APPLICANT
CofO in Progress 4/26/2023 DERRICK SPENCER
Permit Finaled 6/26/2023 DAVID TSAU
CofO Issued 6/26/2023 DAVID TSAU
Permit Finaled 6/26/2023 DAVID TSAU

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/22/2021 ANTHONY MAINEZ
Sewer availability Cleared 11/22/2021 ANTHONY MAINEZ
Green Code Cleared 12/27/2021 JOE VO
Hydrant and Access approval Cleared 12/29/2021 ROBERT DUFF
DAS Clearance Cleared 1/20/2022 JOE VO
Food Service Establishment Cleared 2/7/2022 KENNETH BROWNE
Specific Plan Cleared 2/16/2022 FREDDY GARCIA
Fire Marshal Fire Life Safety Cleared 3/31/2022 WILLIAM JOHNS
Food establishment approval Cleared 4/5/2022 LACDHS APPROVED

Contact Information

Architect Hunt,, David N; Lic. No.: C28367 28636 VIA REGGIO      LAGUNA NIGUEL, CA 92677
Contractor Conam Building Co; Lic. No.: 698311-B 903 CALLE AMANECER STE 210      SAN CLEMENTE, CA 92673
Engineer Escobedo,, Allen; Lic. No.: S5021 11961 PENFORD DR      LA MIRADA, CA 90638

Inspector Information

PAUL DAVIDSON, (310) 914-3914 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/15/2022 Approved PAUL DAVIDSON
Footing/Foundation/Slab 5/18/2022 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 5/23/2022 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 5/23/2022 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 5/27/2022 Conditional Approval DAVID TSAU
Wood Frame 5/31/2022 Conditional Approval PAUL DAVIDSON
Light Gage Steel Frame 7/19/2022 Partial Approval SORIN CIRSTOIU
Insulation 7/27/2022 Partial Approval JEFF BYTHEWAY
Drywall Nailing 8/4/2022 Partial Approval JEFF BYTHEWAY
Light Gage Steel Frame 8/4/2022 Partial Approval JEFF BYTHEWAY
Insulation 8/10/2022 Partial Approval JEFF BYTHEWAY
Drywall Nailing 8/16/2022 Partial Approval JEFF BYTHEWAY
Light Gage Steel Frame 8/25/2022 Partial Approval JEFF BYTHEWAY
Drywall Nailing 8/31/2022 Partial Approval JEFF BYTHEWAY
Deputy Drilled-In Anchors 9/8/2022 Approved JEFF BYTHEWAY
Deputy Drilled-In Anchors 9/9/2022 Approved JEFF BYTHEWAY
Deputy Drilled-In Anchors 9/12/2022 Approved JEFF BYTHEWAY
Deputy Drilled-In Anchors 9/13/2022 Approved JEFF BYTHEWAY
Deputy Drilled-In Anchors 9/14/2022 Approved JEFF BYTHEWAY
Deputy Drilled-In Anchors 9/15/2022 Approved JEFF BYTHEWAY
Deputy Drilled-In Anchors 9/16/2022 Approved JEFF BYTHEWAY
Deputy Drilled-In Anchors 9/19/2022 No Access for Inspection JEFF BYTHEWAY
Deputy Drilled-In Anchors 9/20/2022 Approved DERRICK SPENCER
Deputy Drilled-In Anchors 9/21/2022 Approved DERRICK SPENCER
Deputy Drilled-In Anchors 9/22/2022 Approved DERRICK SPENCER
Deputy Drilled-In Anchors 9/23/2022 Approved DERRICK SPENCER
Deputy Drilled-In Anchors 9/23/2022 Conditional Approval DERRICK SPENCER
Deputy Drilled-In Anchors 9/27/2022 Approved DERRICK SPENCER
Deputy Drilled-In Anchors 9/29/2022 Approved DERRICK SPENCER
T-Bar Ceiling 11/7/2022 Partial Approval DERRICK SPENCER
Final 1/9/2023 Not Ready for Inspection DERRICK SPENCER
Green Building Final 1/9/2023 Not Ready for Inspection DERRICK SPENCER
Green Building Rough 1/9/2023 Approved DERRICK SPENCER
METHANE-Final 1/9/2023 Approved DERRICK SPENCER
METHANE-Rough 1/9/2023 Approved DERRICK SPENCER
Reinforced Masonry Frame 1/9/2023 Approved DERRICK SPENCER
SGSOV-Seismic Gas S/O Valve 1/9/2023 SGSOV Approved DERRICK SPENCER
Smoke Detectors 1/9/2023 Approved DERRICK SPENCER
Final 3/13/2023 Not Ready for Inspection DERRICK SPENCER
Green Building Final 3/13/2023 Not Ready for Inspection DERRICK SPENCER
Final 3/22/2023 Not Ready for Inspection DERRICK SPENCER
Green Building Final 3/22/2023 Not Ready for Inspection DERRICK SPENCER
Final 4/4/2023 Not Ready for Inspection DERRICK SPENCER
Green Building Final 4/4/2023 Not Ready for Inspection DERRICK SPENCER
Final 4/14/2023 OK to Issue CofO DERRICK SPENCER
Green Building Final 4/14/2023 Approved DERRICK SPENCER