977 N BROADWAY 90012

Certificate Information: 977 N BROADWAY 90012

Application / Permit
21016-10000-21882
Plan Check / Job No.
B21LA15673
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
CHANGE OF USE OF EXSITNG 5TH FLOOR CLASSROOM TO OFFICE AND TENANT IMPROVEMENT INCLUDES NEW PARTITION, CEILINGS AND FINISHES THROUGHOUT LEVELS 1 THROUGH 5.
Permit Issued
Issued on 3/31/2022
Issuing Office
Current Status
CofO Issued on 9/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/23/2021 APPLICANT
Green Plans Picked Up 9/3/2021 APPLICANT
Assigned to Plan Check Engineer 9/9/2021 ERIC WONG
Corrections Issued 9/13/2021 ERIC WONG
Quality Review Completed 9/16/2021 PETER KIM
Disabled Access Plans Picked Up 10/7/2021 APPLICANT
Plan Check Approved 3/23/2022 ERIC WONG
Issued 3/31/2022 APPLICANT
Building Plans Picked Up 4/4/2022 APPLICANT
CofO in Progress 9/29/2023 ERNESTO CORRAL
CofO Issued 9/29/2023 ERNESTO CORRAL
Permit Finaled 9/29/2023 ERNESTO CORRAL

Permit Application Clearance Information

Green Code Cleared 9/21/2021 AARON COSTA
Miscellaneous Cleared 10/7/2021 MICAELA TORRES-GIL
Redevelopment Project Area Cleared 10/26/2021 GRACIELA ACOSTA
Eng Process Fee Ord 176,300 Cleared 3/21/2022 CELINA MORENO
Sewer availability Cleared 3/21/2022 CELINA MORENO
DAS Clearance Cleared 3/23/2022 ERIC WONG

Contact Information

Architect Leckie,, David Pentland; Lic. No.: C9183 14348 RIVERSIDE DRIVE # 6      SHERMAN OAKS, CA 91423
Contractor Corporate Contractors Inc; Lic. No.: 604407-B 2550 CORPORATE PL STE C-111      MONTEREY PARK, CA 91754
Engineer Kenyon,, Lance Ritchie; Lic. No.: S3399 3900 COVER STREET      LONG BEACH, CA 90808

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 4/8/2022 Partial Approval MARK FERRARI
Insulation 4/11/2022 Partial Approval MARK FERRARI
Drywall Nailing 4/13/2022 Partial Approval MARK FERRARI
Light Gage Steel Frame 4/25/2022 Partial Approval MARK FERRARI
Drywall Nailing 5/5/2022 Partial Approval MARK FERRARI
Drywall Nailing 5/24/2022 Partial Inspection SORIN CIRSTOIU
Drywall Nailing 5/27/2022 Partial Approval MARK FERRARI
Drywall Nailing 6/3/2022 Partial Approval MARK FERRARI
Light Gage Steel Frame 6/24/2022 Approved RAFAEL ESPINOZA
Drywall Nailing 6/28/2022 Partial Approval MARK FERRARI
Drywall Nailing 7/7/2022 Approved MARK FERRARI
Deputy Drilled-In Anchors 7/13/2022 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 7/14/2022 Partial Approval MARK FERRARI
Light Gage Steel Frame 7/14/2022 Not Ready for Inspection MARK FERRARI
Structural Steel Frame 8/3/2022 Partial Approval MARK FERRARI
Partition/T-Bar Ceiling 8/17/2022 Partial Approval MARK FERRARI
Drywall Nailing 8/22/2022 Partial Approval MARK FERRARI
Drywall Nailing 8/30/2022 Partial Approval ERNESTO CORRAL
Drywall Nailing 9/6/2022 Partial Approval MARK FERRARI
T-Bar Ceiling 9/6/2022 Corrections Issued MARK FERRARI
Drywall Nailing 9/14/2022 Partial Approval MARK FERRARI
T-Bar Ceiling 9/15/2022 Partial Inspection MARK FERRARI
Final 8/24/2023 Conditional Approval ALAN MORELOS
Green Building Final 8/24/2023 Approved ALAN MORELOS
Green Building Rough 8/24/2023 Approved ALAN MORELOS
METHANE-Final 8/24/2023 Approved ALAN MORELOS
METHANE-Rough 8/24/2023 Approved ALAN MORELOS
Reinforced Concrete Frame 8/24/2023 Approved ALAN MORELOS
SGSOV-Seismic Gas S/O Valve 8/24/2023 SGSOV Approved ALAN MORELOS
Smoke Detectors 8/24/2023 Approved ALAN MORELOS