- CHANGE OF USE FROM (E) MANUFACTURING/OFFICE/STORAGE & COMMERCIAL BUILDING TO (N) OFFICE. CORE AND SHELL RENOVATION INCLUDES RECONSTRUCTION FOR PORTION OF MEZZANINE, (N) WINDOWS, SKYLIGHTS, RESTROOMS, MECH, PLATFORMS, ETC. 1 OF 3
- Permit Issued
- Issued on 5/6/2022
- Issuing Office
- Current Status
- Issued on 5/6/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/23/2021 | APPLICANT |
| Green Plans Picked Up | 9/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2021 | JOHNNY WU |
| Disabled Access Plans Picked Up | 9/13/2021 | APPLICANT |
| Corrections Issued | 9/30/2021 | JOHNNY WU |
| Quality Review Completed | 10/1/2021 | FARUK SEZER |
| Applicant returned to address corrections | 10/25/2021 | JOHNNY WU |
| Applicant returned to address corrections | 3/9/2022 | JOHNNY WU |
| Applicant returned to address corrections | 3/11/2022 | JOHNNY WU |
| Applicant returned to address corrections | 3/23/2022 | JOHNNY WU |
| Building Plans Picked Up | 3/25/2022 | APPLICANT |
| Plan Check Approved | 5/6/2022 | JOHNNY WU |
| Issued | 5/6/2022 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/18/2021 | CECILIO NAVARRO |
| Metro Rail approval | Cleared | 11/10/2021 | JOHNNY WU |
| Sewer availability | Cleared | 11/18/2021 | JEANETTE VONG |
| Comm Cor/Mini-Mall | Cleared | 11/19/2021 | JASON CHAN |
| Prkng lot landscape/Water mgmt | Cleared | 11/19/2021 | JASON CHAN |
| ZI | Cleared | 11/19/2021 | JASON CHAN |
| Green Code | Cleared | 2/3/2022 | AARON COSTA |
| DAS Clearance | Cleared | 3/3/2022 | JOHNNY WU |
| Driveway location | Cleared | 4/7/2022 | COLLINS ALLAN |
| Transportation Demand Ord. | Cleared | 4/7/2022 | COLLINS ALLAN |
| Permit | Cleared | 4/25/2022 | CINDY QI |
| Miscellaneous | Cleared | 5/6/2022 | JOHNNY WU |
Contact Information
| Architect | Rhee,, Patricia Soojung; Lic. No.: C29173 | 11345 KINGSLAND STREET LOS ANGELES, CA 90066 |
| Contractor | Lusardi Construction Co; Lic. No.: 207287-B | 1570 LINDA VISTA DRIVE SAN MARCOS, CA 92078 |
| Engineer | Brown,, Wayne Allen; Lic. No.: S6049 | 12221 JUNIPER WAY POWAY, CA 92064 |
| Engineer | Chandra,, Djan; Lic. No.: GE2376 | 3 WATERWAY IRVINE, CA 92614 |
| Engineer | Delgadillo,, Christian; Lic. No.: GE3144 | 10828 CORD AVE DOWNEY, CA 90241 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/8/2022 | Not Ready for Inspection | MARK FERRARI |
| Green Building Rough | 6/27/2022 | Partial Inspection | MARK FERRARI |
| Wood Frame | 6/27/2022 | Partial Approval | MARK FERRARI |
| Green Building Rough | 8/5/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| Wood Frame | 8/5/2022 | Partial Approval | EDWIN GREGORYONA |
| Deputy Drilled-In Anchors | 9/1/2022 | Conditional Approval | WINSTON DUNNING |
| Footing/Foundation/Slab | 9/2/2022 | Partial Approval | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 9/8/2022 | Approved | MARK FERRARI |
| Masonry Wall/Backfill | 9/14/2022 | Approved | MARK FERRARI |
| Drywall Nailing | 9/23/2022 | Partial Approval | MARK FERRARI |
| Deputy Drilled-In Anchors | 9/28/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Footing/Foundation/Slab | 9/28/2022 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 9/29/2022 | Partial Approval | MARK FERRARI |
| Deputy Reinf. Concrete | 10/3/2022 | Approved | MARK FERRARI |
| Footing/Foundation/Slab | 10/3/2022 | Partial Approval | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2022 | Corrections Issued | MARK FERRARI |
| Insulation | 10/7/2022 | Partial Approval | MARK FERRARI |
| Deputy Reinf. Concrete | 10/13/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Footing/Foundation/Slab | 10/13/2022 | Partial Approval | MARK FERRARI |
| Deputy Reinf. Concrete | 10/14/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Footing/Foundation/Slab | 10/17/2022 | Partial Approval | MARK FERRARI |
| Footing/Foundation/Slab | 10/20/2022 | Partial Approval | EDWIN GREGORYONA |
| Interior/Exterior Lathing | 10/20/2022 | Partial Approval | EDWIN GREGORYONA |
| Deputy Drilled-In Anchors | 10/27/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 10/27/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Drilled-In Anchors | 11/7/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Green Building Rough | 11/10/2022 | Partial Inspection | MARK FERRARI |
| Wood Frame | 11/10/2022 | Partial Inspection | MARK FERRARI |
| Deputy Wood Construction | 11/17/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Green Building Rough | 11/18/2022 | Not Ready for Inspection | MARK FERRARI |
| Wood Frame | 11/18/2022 | Not Ready for Inspection | MARK FERRARI |
| Deputy Drilled-In Anchors | 11/21/2022 | Approved | MARK FERRARI |
| Deputy Wood Construction | 11/21/2022 | Conditional Approval | MARK FERRARI |
| Green Building Rough | 11/21/2022 | Partial Inspection | MARK FERRARI |
| Interior/Exterior Lathing | 11/21/2022 | Partial Approval | MARK FERRARI |
| Wood Frame | 11/21/2022 | Partial Approval | MARK FERRARI |
| Insulation | 11/23/2022 | Partial Approval | MARK FERRARI |
| Light Gage Steel Frame | 11/23/2022 | Approved | MARK FERRARI |
| Footing/Foundation/Slab | 12/6/2022 | Partial Approval | MARK FERRARI |
| Interior/Exterior Lathing | 12/8/2022 | Partial Inspection | MARK FERRARI |
| Interior/Exterior Lathing | 12/12/2022 | Partial Approval | MARK FERRARI |
| Interior/Exterior Lathing | 12/19/2022 | Not Ready for Inspection | JEROME BLACKWOOD |
| Interior/Exterior Lathing | 12/21/2022 | Partial Approval | RAFAEL CORTES |
| Excavation/Setback/Form/Re-Bar | 12/29/2022 | Partial Approval | BRUCE CAMPBELL |
| Deputy Reinf. Concrete | 1/3/2023 | Conditional Approval | RAFAEL CORTES |
| Light Gage Steel Frame | 1/4/2023 | Partial Approval | RAFAEL CORTES |
| Deputy Steel/Welding | 1/11/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Drywall Nailing | 1/11/2023 | Partial Approval | RAFAEL CORTES |
| Insulation | 1/11/2023 | Partial Approval | RAFAEL CORTES |
| Deputy Steel/Welding | 1/12/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Drywall Nailing | 1/18/2023 | Partial Approval | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2023 | Partial Approval | EDWIN GREGORYONA |
| Interior/Exterior Lathing | 1/23/2023 | Partial Approval | EDWIN GREGORYONA |
| Light Gage Steel Frame | 1/25/2023 | Partial Approval | RAFAEL CORTES |
| Deputy Wood Construction | 1/26/2023 | Conditional Approval | MARTIN TAVITIAN |
| Insulation | 1/26/2023 | Approved | MARTIN TAVITIAN |
| Deputy Steel/Welding | 1/27/2023 | Conditional Approval | JULIAN CAPUCETTI |
| Deputy Steel/Welding | 1/30/2023 | Conditional Approval | JULIAN CAPUCETTI |
| Drywall Nailing | 2/1/2023 | Approved | RAMAZANALI ALMASI |
| Drywall Nailing | 2/3/2023 | Partial Approval | RAMAZANALI ALMASI |
| Deputy Reinf. Concrete | 2/9/2023 | Conditional Approval | JULIAN CAPUCETTI |
| Deputy Steel/Welding | 2/9/2023 | Conditional Approval | JULIAN CAPUCETTI |
| Footing/Foundation/Slab | 2/9/2023 | Approved | RAMAZANALI ALMASI |
| Footing/Foundation/Slab | 2/14/2023 | Conditional Approval | JULIAN CAPUCETTI |
| Deputy Steel/Welding | 2/15/2023 | Conditional Approval | JULIAN CAPUCETTI |
| Interior/Exterior Lathing | 2/15/2023 | Partial Approval | JAIME RIOS |
| Interior/Exterior Lathing | 2/16/2023 | Approved | RAMAZANALI ALMASI |
| Deputy Steel/Welding | 3/1/2023 | Conditional Approval | JULIAN CAPUCETTI |
| Interior/Exterior Lathing | 3/10/2023 | Partial Inspection | RAFAEL CORTES |
| Reinforced Masonry Frame | 3/20/2023 | Partial Approval | JULIAN CAPUCETTI |
| Footing/Foundation/Slab | 4/6/2023 | Partial Approval | RAFAEL CORTES |
| Structural Steel Frame | 12/27/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Footing/Foundation/Slab | 2/6/2024 | No Access for Inspection | RAFAEL CORTES |
| Reinforced Concrete Frame | 2/6/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Footing/Foundation/Slab | 2/7/2024 | No Access for Inspection | RONALD JIMENEZ |
| Drywall Nailing | 2/27/2024 | Partial Approval | RAMAZANALI ALMASI |
| Drywall Nailing | 2/29/2024 | Partial Approval | RONALD JIMENEZ |
| Insulation | 2/29/2024 | Partial Approval | RONALD JIMENEZ |
| Drywall Nailing | 3/4/2024 | Partial Approval | RAMAZANALI ALMASI |
| Light Gage Steel Frame | 4/1/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |