7824 S BLERIOT AVE 90045
Certificate Information: 7824 S BLERIOT AVE 90045
- Application / Permit
- 21016-10000-21858
- Plan Check / Job No.
- B21LA15652
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE AND STORAGE TO ADU
- Permit Issued
- Issued on 7/18/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/23/2021 | FERNANDO FLORES |
| Corrections Issued | 8/24/2021 | FERNANDO FLORES |
| Applicant returned to address corrections | 10/31/2021 | TSE MING HUANG |
| Plan Check Approved | 11/24/2021 | FERNANDO FLORES |
| Building Plans Picked Up | 12/1/2021 | APPLICANT |
| Issued | 7/18/2022 | APPLICANT |
| CofO in Progress | 8/19/2024 | BOBBY KEY |
| Permit Finaled | 8/22/2024 | RICHARD STEINBACH |
| CofO Issued | 8/22/2024 | RICHARD STEINBACH |
| Permit Finaled | 8/22/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 8/27/2021 | DINAH GARIN |
| Sewer availability | Cleared | 8/27/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 8/31/2021 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 10/27/2021 | TIMOTHY POWELL |
| Construction near power lines | Cleared | 11/13/2021 | RIDWAN HARDY |
| Specific Plan | Cleared | 11/17/2021 | PEDRO AYALA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Braun,, Jason William; Lic. No.: C70948 | 14390 SHAWNEE ST MOORPARK, CA 93021 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/20/2022 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 8/29/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2022 | Partial Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 11/22/2022 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Rough | 11/22/2022 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 11/22/2022 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 11/22/2022 | Approved | BOBBY KEY |
| PLUMBING-Rough | 11/22/2022 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 12/8/2022 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Rough | 12/8/2022 | Not Ready for Inspection | HERBERT GIRON |
| Insulation | 12/8/2022 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Rough | 12/8/2022 | Not Ready for Inspection | HERBERT GIRON |
| BUILDING-Rough-Frame | 12/14/2022 | Conditional Approval | BOBBY KEY |
| ELECTRICAL-Rough | 12/14/2022 | Approved | BOBBY KEY |
| Green Building Rough | 12/14/2022 | Approved | BOBBY KEY |
| HVAC-Final | 12/14/2022 | Corrections Issued | BOBBY KEY |
| Insulation | 12/14/2022 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 12/14/2022 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 12/14/2022 | Conditional Approval | BOBBY KEY |
| Drywall Nailing | 12/20/2022 | Approved | BOBBY KEY |
| Final | 12/20/2022 | Corrections Issued | BOBBY KEY |
| Interior/Exterior Lathing | 12/20/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 3/16/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 3/16/2023 | Approved | BOBBY KEY |
| Final | 3/16/2023 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 3/16/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 3/16/2023 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 3/16/2023 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 3/16/2023 | Corrections Issued | BOBBY KEY |
| Special/Order Compliance | 3/16/2023 | Partial Inspection | JESUS PINEDA |
| Gas Test | 4/14/2023 | No Access for Inspection | BOBBY KEY |
| Sewer | 4/14/2023 | No Access for Inspection | BOBBY KEY |
| Smoke Detectors | 4/14/2023 | No Access for Inspection | BOBBY KEY |
| Final | 8/19/2024 | OK to Issue CofO | BOBBY KEY |
| HVAC-Final | 8/19/2024 | Approved | BOBBY KEY |
| PLUMBING-Final | 8/19/2024 | Approved | BOBBY KEY |
| Smoke Detectors | 8/19/2024 | Approved | BOBBY KEY |