2405 N FORNEY ST 90031

Certificate Information: 2405 N FORNEY ST 90031

Application / Permit
21016-10000-21835
Plan Check / Job No.
B21LA15628
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(12) Food Products Manufacturing
Work Description
*ePlan Check* Tenant Improvement; provide two H/C restrooms, skylights & two A/C, close (e)windows on west, south & north walls, and reconfiguration of east wall
Permit Issued
Issued on 10/8/2021
Issuing Office
Current Status
Permit Finaled on 7/25/2022

Permit Application Status History

Submitted 8/20/2021 APPLICANT
Assigned to Plan Check Engineer 8/20/2021 LARRY LEE
Corrections Issued 8/20/2021 LARRY LEE
Plan Check Approved 9/15/2021 LARRY LEE
Issued 10/8/2021 APPLICANT
Permit Finaled 7/22/2022 MARK FERRARI

Permit Application Clearance Information

Address approval Cleared 10/1/2021 THOMAS LANG

Contact Information

Contractor Owner-Builder       ,
Engineer Hwang,, Junho; Lic. No.: S5592 815 FAIRVIEW AVE #205      SOUTH PASADENA, CA 91030

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/3/2021 Approved BRUCE CAMPBELL
Wood Frame 12/3/2021 Not Ready for Inspection BRUCE CAMPBELL
Wood Frame 12/7/2021 Partial Approval BRUCE CAMPBELL
Deputy Wood Construction 12/10/2021 Approved MARK FERRARI
Wood Frame 12/10/2021 Partial Approval MARK FERRARI
Insulation 12/22/2021 Partial Approval MARK FERRARI
Interior/Exterior Lathing 12/22/2021 Approved MARK FERRARI
Drywall Nailing 1/13/2022 Partial Approval MARK FERRARI
Deputy Drilled-In Anchors 1/31/2022 Approved MARK FERRARI
Footing/Foundation/Slab 1/31/2022 Approved MARK FERRARI
Wood Frame 2/11/2022 Partial Inspection MARK FERRARI
Drywall Nailing 2/28/2022 Approved RAFAEL ESPINOZA
Final 3/15/2022 Partial Inspection MARK FERRARI
SGSOV-Seismic Gas S/O Valve 3/15/2022 SGSOV Not Ready MARK FERRARI
Smoke Detectors 3/15/2022 Approved MARK FERRARI
Final 5/26/2022 Corrections Issued MARK FERRARI
SGSOV-Seismic Gas S/O Valve 5/26/2022 SGSOV Not Ready MARK FERRARI
Final 7/22/2022 Permit Finaled MARK FERRARI
SGSOV-Seismic Gas S/O Valve 7/22/2022 SGSOV No Gas MARK FERRARI