6085 E ROY ST 90042

Certificate Information: 6085 E ROY ST 90042

Application / Permit
21016-10000-21797
Plan Check / Job No.
B21LA15594
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERTE (E) ONE STORY DETACHED GARAGE (427 SQ.FT.) TO ADU PER WFPP (Conversion ofAccessory Building per State Law, CA Govt. Code 65852.2(e)(1)(A))
Permit Issued
Issued on 3/16/2022
Issuing Office
Current Status
CofO Issued on 11/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/23/2021 APPLICANT
Assigned to Plan Check Engineer 8/27/2021 RAHEL BEYENE
Corrections Issued 8/28/2021 RAHEL BEYENE
Applicant returned to address corrections 11/28/2021 AUNG SOE
Plan Check Approved 11/29/2021 AUNG SOE
Building Plans Picked Up 12/8/2021 APPLICANT
Issued 3/16/2022 APPLICANT
CofO in Progress 11/15/2022 CRAIG VAUGHAN
Permit Finaled 11/19/2022 DEROLD HAUFF
CofO Issued 11/19/2022 DEROLD HAUFF
Permit Finaled 11/19/2022 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/25/2021 VASIL MIHALEV
Address approval Cleared 11/6/2021 STEVE MELGAR
Roof/Waste drainage to street Cleared 11/6/2021 STEVE MELGAR
Sewer availability Cleared 11/6/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 11/8/2021 STEVE MELGAR

Contact Information

Contractor Builder 20; Lic. No.: 1023066-B 1817 AVENUE 56      LOS ANGELES, CA 90042

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/4/2022 Not Ready for Inspection CRAIG VAUGHAN
Sewer 5/4/2022 Approved CRAIG VAUGHAN
Underground Mechanical 5/4/2022 Not Ready for Inspection CRAIG VAUGHAN
Gas Test 5/10/2022 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 5/10/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Underground Mechanical 5/10/2022 Partial Approval HAMIK HARTOUNIAN
Underground Mechanical 5/13/2022 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 5/17/2022 No Access for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 5/18/2022 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 6/10/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Footing/Foundation/Slab 7/1/2022 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 8/1/2022 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 8/1/2022 Partial Approval CRAIG VAUGHAN
Gas Test 8/1/2022 Partial Approval CRAIG VAUGHAN
HVAC-Rough 8/1/2022 Corrections Issued CRAIG VAUGHAN
Interior/Exterior Lathing 8/1/2022 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 8/1/2022 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 8/4/2022 Approved CRAIG VAUGHAN
HVAC-Rough 8/4/2022 Approved CRAIG VAUGHAN
Insulation 8/4/2022 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 8/4/2022 Partial Approval CRAIG VAUGHAN
Wood Frame 8/4/2022 Approved CRAIG VAUGHAN
Drywall Nailing 8/9/2022 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 8/9/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Final 9/22/2022 Corrections Issued CRAIG VAUGHAN
Gas Test 9/22/2022 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 9/22/2022 SGSOV Approved CRAIG VAUGHAN
Service/Power Release 9/22/2022 Not Ready for Inspection CRAIG VAUGHAN
Shower Pan 9/22/2022 Approved CRAIG VAUGHAN
Final 10/12/2022 Corrections Issued CRAIG VAUGHAN
Smoke Detectors 10/12/2022 Approved CRAIG VAUGHAN
Final 10/21/2022 Conditional Approval CRAIG VAUGHAN
ELECTRICAL-Final 11/10/2022 Approved CRAIG VAUGHAN
Final 11/10/2022 OK to Issue CofO CRAIG VAUGHAN