6085 E ROY ST 90042
Certificate Information: 6085 E ROY ST 90042
- Application / Permit
- 21016-10000-21797
- Plan Check / Job No.
- B21LA15594
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERTE (E) ONE STORY DETACHED GARAGE (427 SQ.FT.) TO ADU PER WFPP (Conversion ofAccessory Building per State Law, CA Govt. Code 65852.2(e)(1)(A))
- Permit Issued
- Issued on 3/16/2022
- Issuing Office
- Current Status
- CofO Issued on 11/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/27/2021 | RAHEL BEYENE |
| Corrections Issued | 8/28/2021 | RAHEL BEYENE |
| Applicant returned to address corrections | 11/28/2021 | AUNG SOE |
| Plan Check Approved | 11/29/2021 | AUNG SOE |
| Building Plans Picked Up | 12/8/2021 | APPLICANT |
| Issued | 3/16/2022 | APPLICANT |
| CofO in Progress | 11/15/2022 | CRAIG VAUGHAN |
| Permit Finaled | 11/19/2022 | DEROLD HAUFF |
| CofO Issued | 11/19/2022 | DEROLD HAUFF |
| Permit Finaled | 11/19/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/25/2021 | VASIL MIHALEV |
| Address approval | Cleared | 11/6/2021 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 11/6/2021 | STEVE MELGAR |
| Sewer availability | Cleared | 11/6/2021 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 11/8/2021 | STEVE MELGAR |
Contact Information
| Contractor | Builder 20; Lic. No.: 1023066-B | 1817 AVENUE 56 LOS ANGELES, CA 90042 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/4/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Sewer | 5/4/2022 | Approved | CRAIG VAUGHAN |
| Underground Mechanical | 5/4/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Gas Test | 5/10/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 5/10/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Underground Mechanical | 5/10/2022 | Partial Approval | HAMIK HARTOUNIAN |
| Underground Mechanical | 5/13/2022 | Approved | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 5/17/2022 | No Access for Inspection | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 5/18/2022 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 6/10/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 7/1/2022 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 8/1/2022 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 8/1/2022 | Partial Approval | CRAIG VAUGHAN |
| Gas Test | 8/1/2022 | Partial Approval | CRAIG VAUGHAN |
| HVAC-Rough | 8/1/2022 | Corrections Issued | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 8/1/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 8/1/2022 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 8/4/2022 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 8/4/2022 | Approved | CRAIG VAUGHAN |
| Insulation | 8/4/2022 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 8/4/2022 | Partial Approval | CRAIG VAUGHAN |
| Wood Frame | 8/4/2022 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 8/9/2022 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 8/9/2022 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 9/22/2022 | Corrections Issued | CRAIG VAUGHAN |
| Gas Test | 9/22/2022 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 9/22/2022 | SGSOV Approved | CRAIG VAUGHAN |
| Service/Power Release | 9/22/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Shower Pan | 9/22/2022 | Approved | CRAIG VAUGHAN |
| Final | 10/12/2022 | Corrections Issued | CRAIG VAUGHAN |
| Smoke Detectors | 10/12/2022 | Approved | CRAIG VAUGHAN |
| Final | 10/21/2022 | Conditional Approval | CRAIG VAUGHAN |
| ELECTRICAL-Final | 11/10/2022 | Approved | CRAIG VAUGHAN |
| Final | 11/10/2022 | OK to Issue CofO | CRAIG VAUGHAN |