500-512 E 9TH ST 90015

Certificate Information: 500-512 E 9TH ST 90015

Application / Permit
21016-10000-21735
Plan Check / Job No.
B21LA15555
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
FIRE DAMAGE REPAIR OF A 2- STORY COMMERCIAL URM BUILDING: PARTIAL ROOF REPLACEMENT; NEW SPECIAL MOMENT FRAME 4 INCH SHOTCRETE TO URM WALLS.
Permit Issued
Issued on 3/2/2022
Issuing Office
Current Status
Permit Finaled on 11/20/2025

Permit Application Status History

Submitted 8/19/2021 APPLICANT
Assigned to Plan Check Engineer 9/9/2021 KESETE HAREGOT
Corrections Issued 9/13/2021 KESETE HAREGOT
Quality Review Completed 9/16/2021 FARUK SEZER
Disabled Access Plans Picked Up 10/22/2021 APPLICANT
Applicant returned to address corrections 10/27/2021 KESETE HAREGOT
Green Plans Picked Up 1/19/2022 APPLICANT
Plan Check Approved 2/9/2022 KESETE HAREGOT
Plan Check Approved 2/9/2022 KESETE HAREGOT
Issued 3/2/2022 APPLICANT
Building Plans Picked Up 3/3/2022 APPLICANT
Permit Finaled 11/20/2025 PAUL BAZERKANIAN

Permit Application Clearance Information

Historic Resource Verification Cleared 10/6/2021 MICAELA TORRES-GIL
Redevelopment Project Area Cleared 10/7/2021 DAVID URITA
DAS Clearance Cleared 12/29/2021 KESETE HAREGOT
Green Code Cleared 1/19/2022 AARON COSTA

Contact Information

Contractor Optimum Seismic Inc; Lic. No.: 1012702-B 5508 S SANTA FE AVENUE      VERNON, CA 90058
Contractor Owner-Builder       ,
Engineer Mirmohammadsadeghi,, Kamaleddin; Lic. No.: C53468 1377 S BEVERLY GLEN BLVD 308      LOS ANGELES, CA 90024

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/8/2022 Conditional Approval TIMOTHY BUXTON
Deputy Shotcrete 3/18/2022 Conditional Approval TIMOTHY BUXTON
Deputy Steel/Welding 3/21/2022 Conditional Approval TIMOTHY BUXTON
Deputy Steel/Welding 3/31/2022 Conditional Approval TIMOTHY BUXTON
Footing/Foundation/Slab 3/31/2022 Approved DARRYL ARNOLD
Reinforced Concrete Frame 3/31/2022 Approved DARRYL ARNOLD
Deputy Shotcrete 4/7/2022 Conditional Approval DARRYL ARNOLD
Deputy Steel/Welding 4/25/2022 Conditional Approval TIMOTHY BUXTON
Deputy Steel/Welding 4/26/2022 Conditional Approval TIMOTHY BUXTON
Deputy Drilled-In Anchors 5/2/2022 Conditional Approval TIMOTHY BUXTON
Deputy Steel/Welding 5/3/2022 Conditional Approval DARRYL ARNOLD
Footing/Foundation/Slab 5/3/2022 Conditional Approval DARRYL ARNOLD
Structural Steel Frame 5/3/2022 Conditional Approval DARRYL ARNOLD
Deputy Reinf. Concrete 5/4/2022 Conditional Approval TIMOTHY BUXTON
Deputy Drilled-In Anchors 5/16/2022 Conditional Approval TIMOTHY BUXTON
Deputy Steel/Welding 6/1/2022 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 6/2/2022 Conditional Approval TIMOTHY BUXTON
Deputy Steel/Welding 6/7/2022 Conditional Approval TIMOTHY BUXTON
Deputy Steel/Welding 6/8/2022 Conditional Approval TIMOTHY BUXTON
Deputy Wood Construction 6/16/2022 Conditional Approval TIMOTHY BUXTON
Floor/Roof Diaphrgm/Shear Wall 6/17/2022 Approved TIMOTHY BUXTON
Deputy Drilled-In Anchors 6/28/2022 Conditional Approval TIMOTHY BUXTON
Structural Steel Frame 7/1/2022 Approved TIMOTHY BUXTON
Wood Frame 7/1/2022 Approved TIMOTHY BUXTON
Wood Frame 11/10/2022 Partial Inspection ALAN MORELOS
Wood Frame 11/29/2022 Not Ready for Inspection MARK FERRARI
Wood Frame 12/14/2022 Corrections Issued KATY RAMIREZ
Wood Frame 1/19/2023 Partial Approval KATY RAMIREZ
Drywall Nailing 2/7/2023 Partial Approval KATY RAMIREZ
Drywall Nailing 2/17/2023 Partial Approval KATY RAMIREZ
Final 1/23/2025 Not Ready for Inspection PAUL BAZERKANIAN
SGSOV-Seismic Gas S/O Valve 1/23/2025 SGSOV Approved PAUL BAZERKANIAN
Smoke Detectors 1/23/2025 Approved PAUL BAZERKANIAN
Final 3/11/2025 Partial Approval PAUL BAZERKANIAN
Final 3/20/2025 Not Ready for Inspection PAUL BAZERKANIAN
Final 11/20/2025 Permit Finaled PAUL BAZERKANIAN