4025 S BEETHOVEN ST 90066

Certificate Information: 4025 S BEETHOVEN ST 90066

Application / Permit
21016-10000-21712
Plan Check / Job No.
B21LA15536
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL, ADD RESTROOM AND LAUNDRY WITHIN (E) SPACE - REMOVE LOAD BEARING WALL
Permit Issued
Issued on 9/17/2021
Issuing Office
Current Status
Permit Finaled on 8/8/2022

Permit Application Status History

Submitted 8/19/2021 APPLICANT
Assigned to Plan Check Engineer 8/20/2021 DANIEL SANJUAN
Corrections Issued 8/26/2021 DANIEL SANJUAN
Plan Check Approved 9/9/2021 RICARDO RAMIREZ
Issued 9/17/2021 APPLICANT
Building Plans Picked Up 11/10/2021 APPLICANT
Permit Finaled 8/8/2022 JESUS RODRIGUEZ

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Rebuilt Homes Inc; Lic. No.: 1063540-B 2201 N LAKEWOOD BLVD STE D643      LONG BEACH, CA 90815
Engineer Gonzalez,, Felix Bolivar; Lic. No.: C64738 14619 CATALINA AVE      GARDENA, CA 90247

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/17/2021 Not Ready for Inspection ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 11/18/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 12/13/2021 Corrections Issued ENRIQUE MIRELES
HVAC-Rough 12/13/2021 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 12/13/2021 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 12/16/2021 Not Ready for Inspection ENRIQUE MIRELES
HVAC-Rough 12/16/2021 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 12/16/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 12/17/2021 Approved ENRIQUE MIRELES
HVAC-Rough 12/17/2021 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 12/23/2021 Approved ENRIQUE MIRELES
Insulation 12/23/2021 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 1/7/2022 Corrections Issued DAVID FEILER
BUILDING-Rough-Frame 1/12/2022 Approved ENRIQUE MIRELES
Shower Pan 1/12/2022 Corrections Issued ENRIQUE MIRELES
Insulation 1/14/2022 Corrections Issued ENRIQUE MIRELES
Insulation 1/18/2022 Approved ENRIQUE MIRELES
Drywall Nailing 1/31/2022 Approved BRENDAN LOONEY
Interior/Exterior Lathing 2/2/2022 Approved ENRIQUE MIRELES
Shower Pan 2/2/2022 Corrections Issued ENRIQUE MIRELES
Interior/Exterior Lathing 2/3/2022 Not Ready for Inspection ENRIQUE MIRELES
Shower Pan 2/3/2022 Corrections Issued ENRIQUE MIRELES
Interior/Exterior Lathing 2/8/2022 Partial Approval CLAYTON GRAHAM
Shower Pan 2/8/2022 Approved CLAYTON GRAHAM
Interior/Exterior Lathing 2/16/2022 Corrections Issued ENRIQUE MIRELES
Interior/Exterior Lathing 3/3/2022 Approved CLAYTON GRAHAM
Pre-Inspection 5/9/2022 Partial Inspection PATRICK QUALEY
ELECTRICAL-Final 5/13/2022 Corrections Issued STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 5/13/2022 SGSOV Not Ready STEPHANIE SWANSON
Smoke Detectors 5/13/2022 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Final 5/17/2022 Not Ready for Inspection PATRICK QUALEY
ELECTRICAL-Final 5/24/2022 Corrections Issued JESUS RODRIGUEZ
ELECTRICAL-Final 5/26/2022 Approved JESUS RODRIGUEZ
Service/Power Release 5/26/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 6/23/2022 Corrections Issued JESUS RODRIGUEZ
Final 6/23/2022 Corrections Issued JESUS RODRIGUEZ
HVAC-Final 6/23/2022 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Final 6/23/2022 Corrections Issued JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 6/23/2022 SGSOV Not Ready JESUS RODRIGUEZ
Smoke Detectors 6/23/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 7/8/2022 Approved PATRICK QUALEY
Final 7/8/2022 Not Ready for Inspection PATRICK QUALEY
HVAC-Final 7/8/2022 Not Ready for Inspection PATRICK QUALEY
PLUMBING-Final 7/8/2022 Approved PATRICK QUALEY
SGSOV-Seismic Gas S/O Valve 7/8/2022 SGSOV Approved PATRICK QUALEY
Final 8/8/2022 Permit Finaled JESUS RODRIGUEZ