1308 S MEADOWBROOK AVE 90019
Certificate Information: 1308 S MEADOWBROOK AVE 90019
- Application / Permit
- 21016-10000-21711
- Plan Check / Job No.
- B21LA15535
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 23'-8" X 21'-8" 1-CAR GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 10/7/2021
- Issuing Office
- Current Status
- CofO Issued on 1/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/20/2021 | DANIEL SANJUAN |
| Corrections Issued | 8/20/2021 | DANIEL SANJUAN |
| Applicant returned to address corrections | 9/24/2021 | RAMA DABADGE |
| Plan Check Approved | 10/7/2021 | TEODORO DIAZ RODRIGUEZ |
| Issued | 10/7/2021 | APPLICANT |
| CofO in Progress | 9/1/2022 | JOSE AVILA |
| Permit Finaled | 1/7/2023 | DEROLD HAUFF |
| CofO Issued | 1/7/2023 | DEROLD HAUFF |
| Permit Finaled | 1/7/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/17/2021 | THOMAS LANG |
| Sewer availability | Cleared | 9/17/2021 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 9/21/2021 | THOMAS LANG |
| Hold | Cleared | 11/23/2021 | JAZELLE A TRINIDAD |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/1/2021 | Partial Inspection | JOSE AVILA |
| Underground Mechanical | 12/15/2021 | Corrections Issued | JOSE AVILA |
| Sewer | 12/20/2021 | Approved | JOSE AVILA |
| Gas Test | 12/27/2021 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 1/4/2022 | Partial Approval | JOSE AVILA |
| Deputy Drilled-In Anchors | 1/10/2022 | Conditional Approval | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 1/11/2022 | Partial Approval | JOSE AVILA |
| Footing/Foundation/Slab | 1/13/2022 | Approved | JOSE AVILA |
| Deputy Drilled-In Anchors | 1/24/2022 | Conditional Approval | JOSE AVILA |
| Deputy Wood Construction | 1/24/2022 | Conditional Approval | JOSE AVILA |
| PLUMBING-Rough | 2/4/2022 | Approved | JOSE AVILA |
| Rough-Elec/Plmb/HVAC | 2/9/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 2/14/2022 | Partial Approval | JOSE AVILA |
| Green Building Rough | 2/18/2022 | Approved | JOSE AVILA |
| Insulation | 2/18/2022 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 2/18/2022 | Approved | JOSE AVILA |
| Shower Pan | 2/18/2022 | Approved | JOSE AVILA |
| Drywall Nailing | 3/1/2022 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 3/4/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 5/16/2022 | Approved | JOSE AVILA |
| Final | 5/16/2022 | Corrections Issued | JOSE AVILA |
| Green Building Final | 5/16/2022 | Approved | JOSE AVILA |
| METHANE-Final | 5/16/2022 | Approved | JOSE AVILA |
| METHANE-Rough | 5/16/2022 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 5/16/2022 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 5/16/2022 | Corrections Issued | JOSE AVILA |
| Final | 5/18/2022 | Corrections Issued | JOSE AVILA |
| Smoke Detectors | 5/18/2022 | Approved | JOSE AVILA |
| Final | 6/28/2022 | Corrections Issued | JOSE AVILA |
| Final | 9/1/2022 | OK to Issue CofO | JOSE AVILA |