707 S NORTON AVE 90005
Certificate Information: 707 S NORTON AVE 90005
- Application / Permit
- 21016-10000-21516
- Plan Check / Job No.
- B21LA15440
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVENTION FROM BOARDING HOUSE TO SFD INCLUDING INTERIOR REMODEL
- Permit Issued
- Issued on 10/27/2021
- Issuing Office
- Current Status
- CofO Issued on 3/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/8/2021 | ZAW HAN |
| Corrections Issued | 9/14/2021 | ZAW HAN |
| Quality Review Completed | 9/21/2021 | KEN GILL |
| Applicant returned to address corrections | 10/15/2021 | ZAW HAN |
| Plan Check Approved | 10/18/2021 | ZAW HAN |
| Issued | 10/27/2021 | APPLICANT |
| Building Plans Picked Up | 11/1/2021 | APPLICANT |
| CofO in Progress | 2/7/2023 | JEFFREY MEAD |
| CofO Issued | 3/10/2023 | DEROLD HAUFF |
| Permit Finaled | 3/10/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| CPC | Cleared | 9/16/2021 | AMANDA KAINER |
| HPOZ | Cleared | 9/16/2021 | AMANDA KAINER |
| Roof/Waste drainage to street | Cleared | 9/19/2021 | THOMAS LANG |
| Sewer availability | Cleared | 9/19/2021 | THOMAS LANG |
| Specific Plan | Cleared | 9/20/2021 | CHI DANG |
| Eng Process Fee Ord 176,300 | Cleared | 9/21/2021 | THOMAS LANG |
| ZA Case | Cleared | 9/22/2021 | TERRI OSBORNE |
Contact Information
| Contractor | N A N D C O Llc; Lic. No.: 1044615-B | 4836 FULTON AVE SHERMAN OAKS, CA 91423 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/16/2022 | Approved | CHRIS CHRISTENSEN |
| Wood Frame | 5/6/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Wood Frame | 6/1/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Wood Frame | 7/14/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Pre-Inspection | 8/9/2022 | Corrections Issued | JEFFREY MEAD |
| Wood Frame | 8/11/2022 | Approved | JEFFREY MEAD |
| Insulation | 8/17/2022 | Approved | JEFFREY MEAD |
| Drywall Nailing | 8/25/2022 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 8/30/2022 | Partial Approval | JEFFREY MEAD |
| Interior/Exterior Lathing | 9/6/2022 | Approved | JEFFREY MEAD |
| Final | 12/27/2022 | Corrections Issued | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 12/27/2022 | SGSOV Approved | JEFFREY MEAD |
| Smoke Detectors | 12/27/2022 | Approved | JEFFREY MEAD |
| Final | 2/6/2023 | OK to Issue CofO | JEFFREY MEAD |