7825 W 83RD ST 90293
Certificate Information: 7825 W 83RD ST 90293
- Application / Permit
- 21016-10000-21507
- Plan Check / Job No.
- B21LA15426
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Junior Accessory Dwelling Unit
- Work Description
- RESIDENTIAL REMODEL WITH AN ATTACHED CONVERSION TO "JADU" PER GCS65852.2(e)(1)(A) AND 65852.22, . WORK INCLUDES MECHANICAL, ELECTRICAL, PLUMBING, STRUCTURAL, NEW DOORS AND WINDOWS. NO ADDITIONAL.
- Permit Issued
- Issued on 3/18/2022
- Issuing Office
- Current Status
- CofO Issued on 8/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/20/2021 | TSE MING HUANG |
| Corrections Issued | 8/21/2021 | TSE MING HUANG |
| Applicant returned to address corrections | 9/29/2021 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 10/28/2021 | TSE MING HUANG |
| Applicant returned to address corrections | 12/13/2021 | TSE MING HUANG |
| Plan Check Approved | 1/20/2022 | STANLEY RAAP |
| Building Plans Picked Up | 1/25/2022 | APPLICANT |
| Issued | 3/18/2022 | APPLICANT |
| CofO in Progress | 8/15/2024 | BOBBY KEY |
| Permit Finaled | 8/15/2024 | RICHARD STEINBACH |
| CofO Issued | 8/15/2024 | RICHARD STEINBACH |
| Permit Finaled | 8/15/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Specific Plan | Cleared | 9/22/2021 | PETE EYRE |
| Eng Process Fee Ord 176,300 | Cleared | 9/23/2021 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 9/23/2021 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 9/29/2021 | PATRICK MISCHLICH |
Contact Information
| Contractor | Letter Four Inc; Lic. No.: 1028949-B | 12822 WASHINGTN BLVD LOS ANGELES, CA 90066 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/13/2022 | Partial Approval | BOBBY KEY |
| Deputy Drilled-In Anchors | 8/19/2022 | Conditional Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 9/13/2022 | Approved | BOBBY KEY |
| Deputy Reinf. Concrete | 9/15/2022 | Conditional Approval | BOBBY KEY |
| ELECTRICAL-Rough | 10/26/2022 | Approved | BOBBY KEY |
| HVAC-Rough | 11/4/2022 | No Access for Inspection | ANDREW NAVE |
| PLUMBING-Rough | 11/4/2022 | No Access for Inspection | ANDREW NAVE |
| HVAC-Rough | 11/8/2022 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 11/8/2022 | Conditional Approval | BOBBY KEY |
| Deputy Drilled-In Anchors | 12/2/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Final | 3/3/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Rough | 3/3/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 3/3/2023 | Approved | JESUS RODRIGUEZ |
| Special/Order Compliance | 3/3/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 4/21/2023 | Partial Approval | BOBBY KEY |
| METHANE-Rough | 4/21/2023 | Approved | BOBBY KEY |
| Shower Pan | 4/21/2023 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 6/2/2023 | Approved | BOBBY KEY |
| Insulation | 6/2/2023 | Partial Approval | BOBBY KEY |
| Interior/Exterior Lathing | 6/2/2023 | Partial Approval | BOBBY KEY |
| Interior/Exterior Lathing | 6/9/2023 | Approved | KENNETH NAGLE |
| Insulation | 7/5/2023 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 7/18/2023 | Corrections Issued | BOBBY KEY |
| Drywall Nailing | 7/18/2023 | Partial Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 6/7/2024 | Approved | BOBBY KEY |
| Drywall Nailing | 6/7/2024 | Approved | BOBBY KEY |
| Special/Order Compliance | 6/7/2024 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Final | 6/14/2024 | Not Ready for Inspection | HERBERT GIRON |
| Gas Test | 6/14/2024 | Approved | HERBERT GIRON |
| HVAC-Final | 6/14/2024 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 6/14/2024 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 7/25/2024 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 7/25/2024 | Approved | BOBBY KEY |
| PLUMBING-Final | 7/25/2024 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Final | 7/31/2024 | Not Ready for Inspection | BOBBY KEY |
| Final | 7/31/2024 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Final | 7/31/2024 | Not Ready for Inspection | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 7/31/2024 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 7/31/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 8/13/2024 | Approved | BOBBY KEY |
| Final | 8/13/2024 | OK to Issue CofO | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 8/13/2024 | SGSOV Approved | BOBBY KEY |