592 N BEVERLY GLEN BLVD 90077
Certificate Information: 592 N BEVERLY GLEN BLVD 90077
- Application / Permit
- 21016-10000-21492
- Plan Check / Job No.
- B21LA15409
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL OF EXISTING 2 STORY SFD AND EXTERIOR REMODEL TO REPLACE 38 WINDOWS LIKE FOR LIKE, REPLACE 4 NEW WINDOWS PER SPEC, REPLACE 6 DOORS LIKE FOR LIKE, REPLACE 3 NEW DOORS PER SPEC PER ENGINEER DESIGN
- Permit Issued
- Issued on 11/3/2021
- Issuing Office
- Current Status
- Permit Finaled on 1/30/2024
Permit Application Status History
| Submitted | 8/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2021 | ADAM HEGAZI |
| Corrections Issued | 9/3/2021 | STARR CHEN |
| Quality Review Completed | 10/20/2021 | CHRISTOPHER KOMANCHECK |
| Plan Check Approved | 10/25/2021 | ADAM HEGAZI |
| Issued | 11/3/2021 | APPLICANT |
| Building Plans Picked Up | 11/5/2021 | APPLICANT |
| Permit Finaled | 1/29/2024 | BRENDAN LOONEY |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/20/2021 | PATRICK MISCHLICH |
Contact Information
| Architect | Bond,, Dwight S; Lic. No.: C33276 | 1010 SYCAMORE AVENUE # 208 SOUTH PASADENA, CA 91030 |
| Contractor | Dirty Girl Construction Inc; Lic. No.: 934287-B | 4321 STEWART AVENUE LOS ANGELES, CA 90066 |
| Engineer | Phillips,, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/22/2021 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Rough | 1/20/2022 | Corrections Issued | MICHAEL PELHAM |
| PLUMBING-Rough | 1/20/2022 | Corrections Issued | MICHAEL PELHAM |
| ELECTRICAL-Rough | 2/16/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 2/16/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 2/16/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 3/25/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Gas Test | 3/25/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 3/25/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 3/25/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Piling/Pier/Caisson | 3/25/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 5/11/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 5/11/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Gas Test | 5/11/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 5/11/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 5/11/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 5/19/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 5/19/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 5/19/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 7/8/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Gas Test | 7/8/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 7/8/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 7/8/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 7/8/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 7/15/2022 | Partial Approval | KEVIN SARGSYAN |
| Insulation | 8/5/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Drywall Nailing | 9/12/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Shower Pan | 9/12/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Service/Power Release | 9/22/2022 | Not Ready for Inspection | EVAN COOPER |
| Interior/Exterior Lathing | 10/25/2022 | Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 7/18/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Final | 7/18/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| HVAC-Final | 7/18/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Final | 7/18/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 7/18/2023 | SGSOV Not Ready | BRENDAN LOONEY |
| Smoke Detectors | 7/18/2023 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Final | 1/29/2024 | Approved | BRENDAN LOONEY |
| Final | 1/29/2024 | Permit Finaled | BRENDAN LOONEY |
| HVAC-Final | 1/29/2024 | Approved | BRENDAN LOONEY |
| PLUMBING-Final | 1/29/2024 | Approved | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 1/29/2024 | SGSOV Approved | BRENDAN LOONEY |