830 N CRESCENT HEIGHTS BLVD 90046
Certificate Information: 830 N CRESCENT HEIGHTS BLVD 90046
- Application / Permit
- 21016-10000-21440
- Plan Check / Job No.
- B21LA15356
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan CONVERSION OF EXISTING DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(A) COMPLY WITH DEPARTMENT ORDER effective date 03/30/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 9/22/2021
- Issuing Office
- Current Status
- CofO Issued on 2/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/17/2021 | MONICA RAMIREZ |
| Corrections Issued | 8/18/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 9/3/2021 | MONICA RAMIREZ |
| Plan Check Approved | 9/9/2021 | MONICA RAMIREZ |
| Issued | 9/22/2021 | APPLICANT |
| CofO in Progress | 5/19/2023 | PETER RUBIO |
| Permit Finaled | 2/9/2024 | DANIEL SANCHEZ |
| Permit Finaled | 2/9/2024 | DANIEL SANCHEZ |
| CofO Issued | 2/9/2024 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Address approval | Cleared | 8/24/2021 | STEVE MELGAR |
| Sewer availability | Cleared | 8/24/2021 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 8/25/2021 | STEVE MELGAR |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| PETER RUBIO, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN TCHANG, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| RYAN TAGUINES, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/24/2021 | Conditional Approval | TIMOTHY MCCURDY |
| Excavation/Setback/Form/Re-Bar | 11/24/2021 | Approved | TIMOTHY MCCURDY |
| Footing/Foundation/Slab | 11/24/2021 | Approved | TIMOTHY MCCURDY |
| Excavation/Setback/Form/Re-Bar | 12/1/2021 | Approved | PATRICK QUALEY |
| Footing/Foundation/Slab | 12/1/2021 | Approved | PATRICK QUALEY |
| ELECTRICAL-Rough | 12/28/2021 | Corrections Issued | HAGOP BADOSSIAN |
| PLUMBING-Rough | 12/28/2021 | Corrections Issued | HAGOP BADOSSIAN |
| ELECTRICAL-Rough | 1/20/2022 | Corrections Issued | PATRICK QUALEY |
| PLUMBING-Rough | 1/20/2022 | Corrections Issued | PATRICK QUALEY |
| BUILDING-Rough-Frame | 3/16/2022 | Corrections Issued | HAGOP BADOSSIAN |
| Insulation | 3/16/2022 | Approved | HAGOP BADOSSIAN |
| BUILDING-Rough-Frame | 3/31/2022 | Corrections Issued | JOHN TCHANG |
| ELECTRICAL-Rough | 3/31/2022 | Approved | JOHN TCHANG |
| PLUMBING-Rough | 3/31/2022 | Approved | JOHN TCHANG |
| BUILDING-Rough-Frame | 4/8/2022 | Approved | JOHN TCHANG |
| Interior/Exterior Lathing | 4/8/2022 | Approved | JOHN TCHANG |
| Drywall Nailing | 4/28/2022 | Approved | JOHN TCHANG |
| Final | 9/20/2022 | Corrections Issued | JOHN TCHANG |
| SGSOV-Seismic Gas S/O Valve | 9/20/2022 | SGSOV Approved | JOHN TCHANG |
| Smoke Detectors | 9/20/2022 | Approved | JOHN TCHANG |
| Final | 12/6/2022 | Corrections Issued | JOHN TCHANG |
| Gas Test | 12/6/2022 | Approved | JOHN TCHANG |
| Final | 4/13/2023 | No Access for Inspection | PETER RUBIO |
| Final | 5/4/2023 | Corrections Issued | PETER RUBIO |
| Final | 5/15/2023 | Not Ready for Inspection | ROBERT CHAVEZ |
| Final | 5/18/2023 | OK to Issue CofO | PETER RUBIO |