822 E 20TH ST 90011
Certificate Information: 822 E 20TH ST 90011
- Application / Permit
- 21016-10000-21367
- Plan Check / Job No.
- B21LA15292
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (6) Church
- Work Description
- TENANT IMPROVEMENT TO (E) CHURCH & COMMUNITY CENTER FOR ACCESSIBILITY UPGRADES, INTERIOR ALTERATIONS, REMOVAL OF INTERIOR STAIRS TO BE REPLACED WITH NEW ELEVATOR, & RESTRIPING OF PARKING LOT FOR NEW ACCESSIBLE STALL
- Permit Issued
- Issued on 2/23/2022
- Issuing Office
- Current Status
- CofO Issued on 8/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/16/2021 | LAMAR DAVIS |
| Corrections Issued | 9/20/2021 | LAMAR DAVIS |
| Quality Review Completed | 9/29/2021 | KEN GILL |
| Green Plans Picked Up | 10/1/2021 | APPLICANT |
| Plan Check Approved | 2/8/2022 | LAMAR DAVIS |
| Issued | 2/23/2022 | APPLICANT |
| Building Plans Picked Up | 3/9/2022 | APPLICANT |
| CofO in Progress | 8/2/2024 | LUIS CCAMACHO |
| Permit Finaled | 8/5/2024 | ERNESTO CORRAL |
| CofO Issued | 8/5/2024 | ERNESTO CORRAL |
| Permit Finaled | 8/5/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| "Q" conditions | Cleared | 10/18/2021 | DANIEL CORONADO |
| Green Code | Cleared | 11/29/2021 | AARON COSTA |
| DAS Clearance | Cleared | 1/4/2022 | SHINE LIN |
| Fire Marshal Fire Life Safety | Cleared | 1/21/2022 | WILLIAM JOHNS |
Contact Information
| Architect | Brown,, Dale William; Lic. No.: C17744 | 316 N SIERRA MADRE BLVD PASADENA, CA 91107 |
| Contractor | Pankow Charles Builders Ltd; Lic. No.: 688972-B | 199 S LOS ROBLES AVE #300 PASADENA, CA 91101 |
| Engineer | Wirthlin,, Jonathan Daniel; Lic. No.: S5702 | 9340 WOODLEY AVE NORTH HILLS, CA 91343 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/5/2022 | Approved | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 5/6/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 5/10/2022 | Conditional Approval | TIMOTHY BUXTON |
| Excavation/Setback/Form/Re-Bar | 5/10/2022 | Partial Approval | TIMOTHY BUXTON |
| Excavation/Setback/Form/Re-Bar | 5/12/2022 | Conditional Approval | DARRYL ARNOLD |
| Excavation/Setback/Form/Re-Bar | 5/17/2022 | Approved | TIMOTHY BUXTON |
| Excavation/Setback/Form/Re-Bar | 5/18/2022 | Partial Approval | TIMOTHY BUXTON |
| Deputy Reinf. Concrete | 5/20/2022 | Conditional Approval | ERNESTO CORRAL |
| Excavation/Setback/Form/Re-Bar | 5/23/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Deputy Reinf. Concrete | 5/25/2022 | Conditional Approval | TERRY HERR |
| Deputy Reinf. Concrete | 5/26/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Drilled-In Anchors | 6/2/2022 | Conditional Approval | ERNESTO CORRAL |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2022 | Partial Approval | BRUCE CAMPBELL |
| Light Gage Steel Frame | 6/10/2022 | Partial Approval | BRUCE CAMPBELL |
| Wood Frame | 6/10/2022 | Partial Approval | BRUCE CAMPBELL |
| Deputy Drilled-In Anchors | 6/13/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Steel/Welding | 6/21/2022 | Conditional Approval | ERNESTO CORRAL |
| Drywall Nailing | 6/22/2022 | Partial Approval | JONATHAN QUACH |
| T-Bar Ceiling | 6/22/2022 | Approved | JONATHAN QUACH |
| Wood Frame | 6/22/2022 | Partial Approval | JONATHAN QUACH |
| Light Gage Steel Frame | 6/27/2022 | Not Ready for Inspection | MARK FERRARI |
| Insulation | 6/28/2022 | Partial Approval | JONATHAN QUACH |
| Light Gage Steel Frame | 6/28/2022 | Partial Approval | JONATHAN QUACH |
| Drywall Nailing | 7/7/2022 | Partial Approval | JONATHAN QUACH |
| Light Gage Steel Frame | 7/14/2022 | Partial Approval | BRUCE CAMPBELL |
| Drywall Nailing | 7/19/2022 | Off-Hour Fees Due | |
| Drywall Nailing | 7/20/2022 | Conditional Approval | DARRYL ARNOLD |
| Drywall Nailing | 7/22/2022 | Conditional Approval | DARRYL ARNOLD |
| Drywall Nailing | 7/26/2022 | Off-Hour Fees Due | |
| Drywall Nailing | 7/26/2022 | Partial Approval | RUSSELL BONVOULOIR |
| T-Bar Ceiling | 8/9/2022 | Partial Approval | JAMES POWERS |
| Special/Order Compliance | 8/24/2022 | Approved | TIMOTHY BUXTON |
| Final | 12/4/2023 | Corrections Issued | KATY RAMIREZ |
| Green Building Final | 12/4/2023 | Approved | KATY RAMIREZ |
| Green Building Rough | 12/4/2023 | Approved | KATY RAMIREZ |
| Reinforced Masonry Frame | 12/4/2023 | Not Ready for Inspection | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 12/4/2023 | SGSOV Not Ready | KATY RAMIREZ |
| Smoke Detectors | 12/4/2023 | Approved | KATY RAMIREZ |
| Special/Order Compliance | 12/21/2023 | Not Ready for Inspection | KATY RAMIREZ |
| Final | 6/24/2024 | Corrections Issued | LUIS CCAMACHO |
| Reinforced Masonry Frame | 6/24/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| SGSOV-Seismic Gas S/O Valve | 6/24/2024 | SGSOV Not Ready | LUIS CCAMACHO |
| Final | 7/24/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| Reinforced Masonry Frame | 7/24/2024 | Approved | LUIS CCAMACHO |
| SGSOV-Seismic Gas S/O Valve | 7/24/2024 | SGSOV Approved | LUIS CCAMACHO |
| Final | 8/2/2024 | OK to Issue CofO | LUIS CCAMACHO |