822 E 20TH ST 90011

Certificate Information: 822 E 20TH ST 90011

Application / Permit
21016-10000-21367
Plan Check / Job No.
B21LA15292
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(6) Church
Work Description
TENANT IMPROVEMENT TO (E) CHURCH & COMMUNITY CENTER FOR ACCESSIBILITY UPGRADES, INTERIOR ALTERATIONS, REMOVAL OF INTERIOR STAIRS TO BE REPLACED WITH NEW ELEVATOR, & RESTRIPING OF PARKING LOT FOR NEW ACCESSIBLE STALL
Permit Issued
Issued on 2/23/2022
Issuing Office
Current Status
CofO Issued on 8/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/27/2021 APPLICANT
Assigned to Plan Check Engineer 9/16/2021 LAMAR DAVIS
Corrections Issued 9/20/2021 LAMAR DAVIS
Quality Review Completed 9/29/2021 KEN GILL
Green Plans Picked Up 10/1/2021 APPLICANT
Plan Check Approved 2/8/2022 LAMAR DAVIS
Issued 2/23/2022 APPLICANT
Building Plans Picked Up 3/9/2022 APPLICANT
CofO in Progress 8/2/2024 LUIS CCAMACHO
Permit Finaled 8/5/2024 ERNESTO CORRAL
CofO Issued 8/5/2024 ERNESTO CORRAL
Permit Finaled 8/5/2024 ERNESTO CORRAL

Permit Application Clearance Information

"Q" conditions Cleared 10/18/2021 DANIEL CORONADO
Green Code Cleared 11/29/2021 AARON COSTA
DAS Clearance Cleared 1/4/2022 SHINE LIN
Fire Marshal Fire Life Safety Cleared 1/21/2022 WILLIAM JOHNS

Contact Information

Architect Brown,, Dale William; Lic. No.: C17744 316 N SIERRA MADRE BLVD      PASADENA, CA 91107
Contractor Pankow Charles Builders Ltd; Lic. No.: 688972-B 199 S LOS ROBLES AVE #300      PASADENA, CA 91101
Engineer Wirthlin,, Jonathan Daniel; Lic. No.: S5702 9340 WOODLEY AVE      NORTH HILLS, CA 91343

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/5/2022 Approved DARRYL ARNOLD
Deputy Drilled-In Anchors 5/6/2022 Conditional Approval DARRYL ARNOLD
Deputy Reinf. Concrete 5/10/2022 Conditional Approval TIMOTHY BUXTON
Excavation/Setback/Form/Re-Bar 5/10/2022 Partial Approval TIMOTHY BUXTON
Excavation/Setback/Form/Re-Bar 5/12/2022 Conditional Approval DARRYL ARNOLD
Excavation/Setback/Form/Re-Bar 5/17/2022 Approved TIMOTHY BUXTON
Excavation/Setback/Form/Re-Bar 5/18/2022 Partial Approval TIMOTHY BUXTON
Deputy Reinf. Concrete 5/20/2022 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 5/23/2022 Partial Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 5/25/2022 Conditional Approval TERRY HERR
Deputy Reinf. Concrete 5/26/2022 Conditional Approval ERNESTO CORRAL
Deputy Drilled-In Anchors 6/2/2022 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 6/10/2022 Partial Approval BRUCE CAMPBELL
Light Gage Steel Frame 6/10/2022 Partial Approval BRUCE CAMPBELL
Wood Frame 6/10/2022 Partial Approval BRUCE CAMPBELL
Deputy Drilled-In Anchors 6/13/2022 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 6/21/2022 Conditional Approval ERNESTO CORRAL
Drywall Nailing 6/22/2022 Partial Approval JONATHAN QUACH
T-Bar Ceiling 6/22/2022 Approved JONATHAN QUACH
Wood Frame 6/22/2022 Partial Approval JONATHAN QUACH
Light Gage Steel Frame 6/27/2022 Not Ready for Inspection MARK FERRARI
Insulation 6/28/2022 Partial Approval JONATHAN QUACH
Light Gage Steel Frame 6/28/2022 Partial Approval JONATHAN QUACH
Drywall Nailing 7/7/2022 Partial Approval JONATHAN QUACH
Light Gage Steel Frame 7/14/2022 Partial Approval BRUCE CAMPBELL
Drywall Nailing 7/19/2022 Off-Hour Fees Due
Drywall Nailing 7/20/2022 Conditional Approval DARRYL ARNOLD
Drywall Nailing 7/22/2022 Conditional Approval DARRYL ARNOLD
Drywall Nailing 7/26/2022 Off-Hour Fees Due
Drywall Nailing 7/26/2022 Partial Approval RUSSELL BONVOULOIR
T-Bar Ceiling 8/9/2022 Partial Approval JAMES POWERS
Special/Order Compliance 8/24/2022 Approved TIMOTHY BUXTON
Final 12/4/2023 Corrections Issued KATY RAMIREZ
Green Building Final 12/4/2023 Approved KATY RAMIREZ
Green Building Rough 12/4/2023 Approved KATY RAMIREZ
Reinforced Masonry Frame 12/4/2023 Not Ready for Inspection KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 12/4/2023 SGSOV Not Ready KATY RAMIREZ
Smoke Detectors 12/4/2023 Approved KATY RAMIREZ
Special/Order Compliance 12/21/2023 Not Ready for Inspection KATY RAMIREZ
Final 6/24/2024 Corrections Issued LUIS CCAMACHO
Reinforced Masonry Frame 6/24/2024 Not Ready for Inspection LUIS CCAMACHO
SGSOV-Seismic Gas S/O Valve 6/24/2024 SGSOV Not Ready LUIS CCAMACHO
Final 7/24/2024 Not Ready for Inspection LUIS CCAMACHO
Reinforced Masonry Frame 7/24/2024 Approved LUIS CCAMACHO
SGSOV-Seismic Gas S/O Valve 7/24/2024 SGSOV Approved LUIS CCAMACHO
Final 8/2/2024 OK to Issue CofO LUIS CCAMACHO