737 N WESTERN AVE 90029
Certificate Information: 737 N WESTERN AVE 90029
- Application / Permit
- 21016-10000-21297
- Plan Check / Job No.
- B21LA15234
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- T.I TO (E) URM RETAIL BUILDING. : INSTALLING NEW DEMISING WALLS TO CREATE 3 NEW RETAIL TENANT SPACES & NEW OPENINGS IN EXTERIOR WALLS, & MODIFICATION TO ROOF DIAPHRAGM, AND COMPLETE INTERIOR REMODEL. NO CHANGE OF USE, NO ADDITIONAL FLOOR AREA, NO CHANGE IN PARKING.
- Permit Issued
- Issued on 6/16/2022
- Issuing Office
- Metro
- Current Status
- Issued on 6/16/2022
Permit Application Status History
| Submitted | 8/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/16/2021 | GARO TELMI |
| Corrections Issued | 9/23/2021 | GARO TELMI |
| Quality Review Completed | 9/29/2021 | KEN GILL |
| Disabled Access Plans Picked Up | 9/30/2021 | APPLICANT |
| Applicant returned to address corrections | 10/28/2021 | GARO TELMI |
| Green Plans Picked Up | 12/22/2021 | APPLICANT |
| Applicant returned to address corrections | 3/18/2022 | GARO TELMI |
| Plan Check Approved | 3/25/2022 | GARO TELMI |
| Issued | 6/16/2022 | APPLICANT |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 10/6/2021 | MICAELA TORRES-GIL |
| Eng Process Fee Ord 176,300 | Cleared | 10/18/2021 | CECILIO NAVARRO |
| Green Code | Cleared | 11/10/2021 | AARON COSTA |
| Redevelopment Project Area | Cleared | 11/15/2021 | GRACIELA ACOSTA |
| ZI | Cleared | 11/15/2021 | GRACIELA ACOSTA |
| "D" conditions | Cleared | 11/17/2021 | DANIEL CORONADO |
| Miscellaneous | Cleared | 11/17/2021 | DANIEL CORONADO |
| DAS Clearance | Cleared | 1/26/2022 | GARO TELMI |
| Low Impact Development | Cleared | 3/2/2022 | JORGE MEJIA LEMUS |
| Address approval | Cleared | 3/3/2022 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 3/3/2022 | JEANETTE VONG |
Contact Information
| Architect | Raabe,, Evan A; Lic. No.: C32671 | 1528 SHADOW LANE FULLERTON, CA 92831 |
| Contractor | Mata Contracting Corporation; Lic. No.: 966590-B | 318 EAST GLENOAKS BLVD SUITE 201 GLENDALE, CA 91207 |
| Engineer | Cassman,, Jessica Akemi; Lic. No.: C73907 | 201 W HARVEY AVE SANTA ANA, CA 92707 |
| Engineer | Chen,, Jeff Y; Lic. No.: S4699 | 17500 REDHILL AVENUE SUITE 240 IRVINE, CA 92614 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/21/2022 | Partial Approval | JONATHAN QUACH |
| Footing/Foundation/Slab | 6/21/2022 | Corrections Issued | JONATHAN QUACH |
| Deputy Reinf. Concrete | 6/28/2022 | Conditional Approval | ERNESTO CORRAL |
| Wood Frame | 6/28/2022 | Partial Approval | EDWIN GREGORYONA |
| Deputy Drilled-In Anchors | 6/29/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Steel/Welding | 6/29/2022 | Conditional Approval | ERNESTO CORRAL |
| Wood Frame | 7/6/2022 | Partial Approval | JONATHAN QUACH |
| Deputy Drilled-In Anchors | 8/2/2022 | Conditional Approval | JONATHAN QUACH |
| Deputy Steel/Welding | 8/2/2022 | Conditional Approval | JONATHAN QUACH |
| Excavation/Setback/Form/Re-Bar | 8/2/2022 | Partial Approval | JONATHAN QUACH |
| Deputy Reinf. Concrete | 8/29/2022 | Conditional Approval | WINSTON DUNNING |
| Deputy Drilled-In Anchors | 9/28/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Footing/Foundation/Slab | 9/28/2022 | Partial Approval | JONATHAN QUACH |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2022 | Partial Approval | JONATHAN QUACH |
| Deputy Drilled-In Anchors | 10/13/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Drilled-In Anchors | 10/27/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Drilled-In Anchors | 11/2/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Excavation/Setback/Form/Re-Bar | 11/2/2022 | Not Ready for Inspection | JONATHAN QUACH |
| Excavation/Setback/Form/Re-Bar | 11/4/2022 | Partial Approval | JONATHAN QUACH |
| Light Gage Steel Frame | 11/8/2022 | Partial Approval | MARK FERRARI |
| Drywall Nailing | 11/28/2022 | Partial Approval | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2022 | Partial Inspection | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2022 | Partial Inspection | JONATHAN QUACH |
| Deputy Wood Construction | 12/15/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Drywall Nailing | 12/20/2022 | Partial Approval | RONALD JIMENEZ |
| Interior/Exterior Lathing | 2/9/2023 | Approved | MARTIN TAVITIAN |
| Light Gage Steel Frame | 2/24/2023 | Partial Approval | TIMOTHY POWELL |
| Drywall Nailing | 2/28/2023 | Partial Approval | BRUCE CAMPBELL |
| Light Gage Steel Frame | 2/28/2023 | Partial Approval | BRUCE CAMPBELL |
| Drywall Nailing | 3/7/2023 | Partial Approval | MARTIN TAVITIAN |
| Special/Order Compliance | 3/14/2023 | Partial Inspection | GREGORY POMISH |
| Interior/Exterior Lathing | 4/3/2023 | Partial Approval | MARTIN TAVITIAN |
| Final | 5/27/2023 | Not Ready for Inspection | MARTIN TAVITIAN |
| Green Building Final | 5/27/2023 | Approved | MARTIN TAVITIAN |
| SGSOV-Seismic Gas S/O Valve | 5/27/2023 | SGSOV Approved | MARTIN TAVITIAN |
| Final | 5/30/2023 | Partial Approval | MARTIN TAVITIAN |
| SGSOV-Seismic Gas S/O Valve | 5/30/2023 | SGSOV Approved | MARTIN TAVITIAN |
| Smoke Detectors | 5/30/2023 | Partial Approval | MARTIN TAVITIAN |
| Green Building Final | 5/31/2023 | Approved | MARTIN TAVITIAN |
| Smoke Detectors | 5/31/2023 | Approved | MARTIN TAVITIAN |
| Final | 1/8/2026 | Not Ready for Inspection | LUIS CCAMACHO |
| Smoke Detectors | 1/8/2026 | Not Ready for Inspection | LUIS CCAMACHO |
| Final | 2/9/2026 | Not Ready for Inspection | LUIS CCAMACHO |
| Smoke Detectors | 2/9/2026 | Not Ready for Inspection | LUIS CCAMACHO |
| Final | 2/26/2026 | Partial Inspection | LUIS CCAMACHO |
| Smoke Detectors | 2/26/2026 | Approved | LUIS CCAMACHO |